
Review Questions to Support Training Modules
ICE Analysis Training - Spring 2007
Introduction and FHWA Portion
1. True or False - ICE Analysis scoping activities begin after the alternatives Retained for a Detailed Study are selected for a given project?
Answer
2. SHA's ICE Analysis Guidelines apply to which of the following NEPA Documents?
- Environmental Impact Statements (EIS) and Environmental Assessments (EA's) only
- Environmental Impact Statements only
- Environmental Impact Statements, Environmental Assessments, Categorical Exclusions (CE's) and Environmental Re-Evaluations (ER's)
- Categorical Exclusions only
Answer
3. True or False - There is a single, universal approach to conducting an ICE Analysis.
Answer
4. True or False - To date, indirect and cumulative effects analyses have not been challenged in the federal court.
Answer
5. True or False - FHWA provides numerous resources on their website for guidance on ICE analyses.
Answer
Module 1:
1. True or False - Direct Impacts do not have to be factored into a Secondary and Cumulative Effects Analysis.
Answer
2. Which of the following is not considered a resource for the purpose of an ICE Analysis?
- Historic Sites
- Wetlands
- Groundwater
- Air Quality
- Floodplains
Answer
3. True or False - Those resources that are directly impacted by a project alternative should also be considered for potential cumulative impacts.
Answer
4. True or False - Land use can be considered a resource if the future land use scenario is significantly different than the existing land use scenario.
Answer
5. True or False - SHA Guidelines provide a master list of resources that should be included for analysis in every ICE Analysis that is conducted in Maryland.
Answer
6. Which data source would be considered for providing readily available data in determining resources to consider?
- Local Master Plans
- Correspondence with Local Planners
- Census Data
- FEMA Maps
- All of the above
Answer
Module 2:
1. True or False - There can be multiple geographical boundaries, depending on whether natural environmental, socio-economic or cultural resources are being analyzed in the ICE Analysis.
Answer
2. True or False - Subwatersheds are an appropriate sub-boundary to help establish an overall ICE Analysis geographical boundary.
Answer
3. Which of the following is not considered an appropriate sub-boundary for the purposes of developing an ICE Analysis geographical boundary?
- Area of Traffic Influence
- Extent of Preliminary Alternatives
- Sewer/Water Servic
- Roads
- Sub-Watersheds
Answer
4. True or False - The area of traffic influence has to be considered in the development of an ICE Analysis geographical boundary only when the project alternative is going to increase travel capacity.
Answer
5. True or False - Mapping that shows extent of a preliminary/conceptual alternative is useful in establishing an ICE Analysis geographical boundary.
Answer
6. Which of the following boundaries would likely be considered in developing the ICE Analysis Boundary?
- Metropolitan Area
- Election Districts
- County Boundaries
- Municipalities
- Census Tracts
Answer
7. Which of the following is likely to set the outermost limit of the ICE Analysis Boundary?
- Area of Traffic Influence
- Census Tracts
- Sub-Watersheds
- Planning Areas
- None of the above
Answer
Module 3:
1. True or False - When determining your ICE Analysis time frame, the availability of data is the only factor that should be considered.
Answer
2. Which of the following is not appropriate in establishing an ICE Analysis time frame?
- Input from local planners
- The design year of a project
- Availability of data
- Year in which this project's NEPA documentation is completed
- Major events in the general project area
- Significant land use or population changes
Answer
3. True or False - It is recommended that information about changes in land use or population that substantiate the selection of a major event in establishing an ICE Analysis time frame be included as part of the ICE Analysis documentation.
Answer
4. True or False - You should never consider available resource trends data for your ICE Analysis that proceeds the past year time frame.
Answer
5. True or False - The future year time frame is always set as the year 2030.
Answer
6. Which would not be a likely factor in determining the Past ICE Analysis Time Frame?
- Adoption of a Master Plan
- Establishment of a building moratorium
- Past highway widening
- Appointment of a new Planning Director
- Construction of a major mixed-use development
Answer
7. Why is population a factor in establishing a timeframe?
- Population growth is relevant to infrastructural needs
- Population growth is relevant to construction trends
- Population growth is relevant to increases in traffic
- Population data is readily available from the US Census
- All of the above
Answer
8. True or False - The opening of a military base should not be a consideration when determining the past time frame.
Answer
Module 4:
1. True or False - When developing your future land use scenario, development planned 4 years from the current year should be included.
Answer
2. True or False - Land use scenarios for the present time period must always be developed, but scenarios for the past and future are developed on a project by project basis.
Answer
3. True or False - Expert land use panels are expected to be created to support the development of land use for all ICE Analyses.
Answer
4. True or False - When developing your land use, it is possible that each alternative may result in its own land use scenario.
Answer
5. True or False - 500 residential units is the minimum threshold when establishing a future land use scenario for all ICE Analyses in the State of Maryland.
Answer
6. Which is not a land use category that should be considered in the ICE Analysis?
- Historic Boundaries
- Parkland
- Institutional
- Residential
- Woodland
Answer
Module 5:
1. True or False - In cases where resource data is deficient, it is recommended to develop models to address these data gaps.
Answer
2. True or False - Qualitative analysis is recommended for the assessment of resources only when all attempts at quantitative analysis are exhausted.
Answer
3. True or False - The ICE Analysis Geographical Boundary established during the scoping process can't be adjusted during the analysis phase of the ICE Analysis.
Answer
4. True or False - Predicting impacts to resources based on current trends should consider the effects of regulatory programs.
Answer
5. True or False - Current SHA Guidelines recommend overlay, trends, interviews and matrices as the four main analysis methodologies.
Answer
6. When should the analysis phase begin?
- During the development of Preliminary Alternatives
- After concurrence on Alternatives Retained for Detailed Study
- After the Public Informational Workshops
- After completion of the DEIS
- After an Alternative has been selected
Answer
7. If multiple consultants are used during the study, which consultant team is most appropriate for developing the ICE Analysis?
- Travel Forecasting Consultant
- Natural Resources Consultant
- Socioeconomic Resources Consultant
- Cultural Resources Consultant
- Environmental Management Team
Answer
8. True or False - ICE Analysis conclusions should be reached in consultation with project team members along with agency comments.
Answer
Module 6:
1. True or False - Under current SHA Guidelines, documentation of an ICE Analysis is separated into the primary sections of Scoping, Analysis, Mitigation and Conclusions.
Answer
2. True or False - SHA requires that a stand-alone ICE Analysis Technical Report be prepared similar to socio-economic, natural environmental, noise quality and air quality technical reports.
Answer
3. True or False - It is not necessary to provide any background information that is pertinent to the resource in the documentation.
Answer
4. True of False - Documentation of resource impacts should be developed for each individual resource and alternative.
Answer
5. True or False - Organization of the ICE Analysis documentation requires that indirect and cumulative resource impacts be discussed within each section relevant to the resources considered.
Answer
6. True or False - The "judicious" use of tables and graphics in the ICE Analysis narrative is encouraged.
Answer
7. True or False - Meeting summaries from discussions with local jurisdictions should not be included in the ICE Analysis documentation.
Answer
8. True or False - Mapping for the geographical boundary is the only necessary mapping that should be included in the analysis.
Answer
Module 7:
1. True or False - Mitigation of indirect and cumulative effects is a requirement of NEPA.
Answer
2. True or False - Possible mitigation strategies can be coordinated with local jurisdictions/agencies if indirect and cumulative effects are identified.
Answer
3. True or False - The development of resource preservation plans through coordinating with local jurisdictions is not a realistic mitigation strategy.
Answer
4. True or False - The mitigation discussion should include existing regulations and protective measures.
Answer