MARYLAND STATE HIGHWAY ADMINISTRATION          
OFFICE OF HIGHWAY DEVELOPMENT          
DESIGN TECHNICAL SERVICES DIVISION          
707 NORTH CALVERT STREET          
BALTIMORE, MARYLAND 21202          
          
November 17, 2014          
          
Contract No. XX1605174          
Description: Stormwater/Drainage Asset Remediation at Various Locations Statewide          
Drainage Improvements          
          
ADDENDUM NO. 1          
          
To All Purchasers of Contract Documents:          
          
Please be advised that the Bid Opening date for this contract is still           
scheduled for November 25, 2014.          
          
The attention of prospective bidders is directed to the following           
revisions, additions and/or deletions to the Invitation for Bids book.          
          
SCHEDULE OF PRICES          
          
Note: For your convenience a NEW abbreviated list has been posted on the           
SHA Web site at www.roads.maryland.gov, under the “Business Center” page,           
under “Contracts, Bids & Proposals – Construction Contracts – Project           
Quantities.”           
          
Page No. Description          
          
298 REVISED the Pre-established Price of Item No. 3003 (300000)           
“SUBCONTRACTORS FOR SPECIALIZED CONSTRUCTION” from to $0 to           
$270,000.00.          
          
CONTRACTOR QUESTIONS          
          
INCLUDED IN THIS RESPONSE ARE CONTRACTOR QUESTIONS RECEIVED AS OF           
11/12/2014.          
          
The following questions were received from plan purchasers. The responses           
are provided for clarification to all bidders in bold after the           
questions:          
          
Q 1: Special Provisions – Subcontractors for Specialized Construction 9           
(page 181) under measurement for payment states that the price for this           
item had been established & not altered by the contractor. The proposal           
form item 3003 subcontractors for specialized construction (page 298) has           
a quantity of 1 but no price has been established on the form. Does SHA           
intent to establish a price?          
          
          
A1: Page 298 was revised to add the pre-established price for Item No.           
3003 (300000) “SUBCONTRACTORS FOR SPECIALIZED CONSTRUCTION” of           
$270,000.00.          
          
Q 2: Are material suppliers who deliver their products to project sites           
required to pay their drivers the applicable prevailing wage rate and           
provide certified payrolls for these drivers?          
          
A2: No.          
          
Q3: Is the Prime Contractor or any Subcontractor delivering materials           
to project sites or between project sites material required to pay their           
drivers the applicable prevailing wage rate and provide certified           
payrolls for these drivers?          
          
A3: No.          
          
Before submitting your bid, please remove any existing Invitation for           
Bids pages that have been replaced by this Addendum No. 1, and insert the           
revised Invitation for Bids pages in their proper sequence. Attach this           
Addendum letter to the front of your Invitation for Bids booklet.          
          
Questions relating to this Addendum No. 1 may be directed in writing to:          
          
Mr. Jason Ridgway          
Director, Office of Highway Development          
707 North Calvert Street          
Baltimore, Maryland 21202          
ATTN: Mr. Cornelius Barmer          
          
If time is of the essence, handwritten questions may be transmitted to           
FAX No. 410-209-5001. All questions are to be addressed to Mr. Cornelius           
Barmer, and the Contractor must identify the source of the question and           
the contract number.          
          
          
          
DOUGLAS H. SIMMONS, CHIEF ENGINEER/DEPUTY ADMINSTRATOR FOR PLANNING AND           
ENGINEERING, REAL ESTATE, AND ENVIRONMENT. REPORT OF DELIVERY REQUESTED           
TO VERIFY THAT THE ADDENDUM WAS RECEIVED, PLEASE CALL 410-467-8000.