Home
Business Center
Projects & Studies
Commuter & Travel
Safety Programs
Environment & Community
Info Center
State Highway Administration
business center
Projects & Studies
commuter & travel
safety programs
environment & Community
information center
contact us

Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Washington Project Number:WA216_51
IS 0070 EISENHOWER MEMORIAL HIGHWAY BRIDGE 2107304 AND BRIDGE 2114204 OVER I-81
Status
10/26/2017The project is 43% complete.

Recently Completed Work:
-Placed concrete for new parapet wall.
-Placed stone base and paved bridge approaches.
-Installed new guardrail at bridge approach.

Upcoming Work
-Install containment system for cleaning and painting of structural steel beams.
-Clean and paint beams.
-Return traffic to original configuration before Thanksgiving.
-Begin work on I-70 WB bridge in Spring, 2018.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way
Construction Spring 2017 Summer 2019
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
10/26/2017The project is 43% complete.

Recently Completed Work:
-Placed concrete for new parapet wall.
-Placed stone base and paved bridge approaches.
-Installed new guardrail at bridge approach.

Upcoming Work
-Install containment system for cleaning and painting of structural steel beams.
-Clean and paint beams.
-Return traffic to original configuration before Thanksgiving.
-Begin work on I-70 WB bridge in Spring, 2018.
 
8/22/2017The project is now 26% Complete.

Current Work
Phase 1 deck replacement is complete.
Project now working in Phase 2 (left lane is closed.)
Removed existing approach roadway, bridge deck, parapet wall, and abutment wingwall.

Upcoming Work
Install forms and place concrete for new pier caps.
Weld new bearing plates and stiffener plates for structural steel.
Begin repair of existing piers.
 
6/12/2017The job is 9% Complete


Current Work
The bridge deck has been removed.
Phase 1 pier cap concrete repairs are complete.


Upcoming Work
Place concrete for Phase 1 back walls.
Phase 1 bearing replacement.
Installation of deck pans.
Fiber wrap on pier caps.
Substructure repairs.
 
1/1/2016Engineering underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202