Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:St. Mary's Project Number:SM774_21
MD 0005 POINT LOOKOUT ROAD THE CAUSEWAY TO SOUTH OF CAMP BROWN ROAD
Status
9/5/2017The next design milestone, 90% design completion, will be in late Fall 2017. There has been continued coordination with the Department of Natural Resources and other environmental agencies as the project progresses. A public meeting is anticipated to be held in Fall 2017. A newsletter will be sent to residents with the date and location prior to the public meeting. Wetland mitigation site search is ongoing. The project is fully funded for construction with an anticipated start date of Fall 2018.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning Complete
Engineering Underway 2018
Right-of-Way Underway 2020
Construction 2019 2021
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic: Spring
 
Status Updates
 
9/5/2017The next design milestone, 90% design completion, will be in late Fall 2017. There has been continued coordination with the Department of Natural Resources and other environmental agencies as the project progresses. A public meeting is anticipated to be held in Fall 2017. A newsletter will be sent to residents with the date and location prior to the public meeting. Wetland mitigation site search is ongoing. The project is fully funded for construction with an anticipated start date of Fall 2018.
 
4/14/2017The next design milestone, 65% design completion, will be held in April 2017. There has been continued coordination with the Department of Natural Resources and other environmental agencies as the project progresses. A public meeting is anticipated to be held in late Summer/early Fall 2017. The project is fully funded for construction with an anticipated start date of Fall 2018.
 
11/28/2016The next design milestone, 65% design completion, will be held in January 2017. There has been continued coordination with the Department of Natural Resources and other environmental agencies as the project progresses. The project is funded for construction with an anticipated Advertisement in Summer 2018.
 
6/22/2016The 30% design milestone was held in April 2016, with a project team field walk following the meeting. There has been continued coordination with the Department of Natural Resources and other environmental agencies as the project progresses. The next design milestone, 65% design completion, will be held in January 2017. The project is funded for construction, with an anticipated Advertisement in Summer 2018.
 
3/9/2016The project has been funded for construction, with an anticipated Advertisement in Summer 2018. The next design milestone is Preliminary Investigation (30% design), and it will be held in April 2016. Construction is anticipated to begin in Fall 2018.
 
9/1/2015Project has been funded for Right of Way and Construction.
 
5/13/2015Design Initiation held on 1/21/15.
 
1/9/2015Project has been funded for design.
 


Events

   Community Informational Meeting

Date:

11/2/2017
Location:13820 Point Lookout Road, Ridge ,MD 20680
 
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202