Home
Business Center
Projects & Studies
Commuter & Travel
Safety Programs
Environment & Community
Info Center
State Highway Administration
business center
Projects & Studies
commuter & travel
safety programs
environment & Community
information center
contact us

Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Queen Anne's Project Number:QA291_51
MD 0213 CENTERVILLE ROAD BRIDGES OVER GRAVEL RUN AND OLD MILL STREAM
Status
6/4/2019The third of four planned weekend closures for the Gravel Run bridge replacement is scheduled for the weekend of June 7-10. Weather permitting, SHA will close MD 213 just south of MD 305 at 7 p.m. Friday, June 7. Work includes removal of the temporary "jump" bridge and restoration of the roadway to original grade. When MD 213 reopens by 5 a.m. Monday morning drivers will be using the new bridge. Temporary concrete barrier will still be in place along the bridge sides and crews will continue working behind this barrier during the week to finish the new parapets (side walls) and lighting. One more weekend closure should be needed for guardrail installation and final surface paving/striping of the bridge approach roadway.

At the south end of town, overnight lane closures and flagging continue as the Old Mill Stream site is readied for the new bridge which is under construction in the staging area across from Citgo. Once the weekend closures at Gravel Run are completed we'll schedule the first of four weekend closures for the Old Mill Stream bridge.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Underway 2019
Right-of-Way
Construction Fall 2018 Fall 2019
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
6/4/2019The third of four planned weekend closures for the Gravel Run bridge replacement is scheduled for the weekend of June 7-10. Weather permitting, SHA will close MD 213 just south of MD 305 at 7 p.m. Friday, June 7. Work includes removal of the temporary "jump" bridge and restoration of the roadway to original grade. When MD 213 reopens by 5 a.m. Monday morning drivers will be using the new bridge. Temporary concrete barrier will still be in place along the bridge sides and crews will continue working behind this barrier during the week to finish the new parapets (side walls) and lighting. One more weekend closure should be needed for guardrail installation and final surface paving/striping of the bridge approach roadway.

At the south end of town, overnight lane closures and flagging continue as the Old Mill Stream site is readied for the new bridge which is under construction in the staging area across from Citgo. Once the weekend closures at Gravel Run are completed we'll schedule the first of four weekend closures for the Old Mill Stream bridge.
 
4/1/2019MD 213 CLOSURE UPDATE
Please see the closure/detour map on the "Maps" tab of this project website.

The first of four planned weekend MD 213 closures at Gravel Run will begin Friday, April 5 at 7 p.m. and continue through the weekend. MD 213 will reopen by 5 a.m. Monday morning, April 8. Detour signs will be posted. Commercial truck drivers passing through Centreville over the weekend may want to avoid using MD 304/Water Street in town due to limited turning radius. Stay on US 301 if possible.

Crews will use this closure to install a temporary "jump bridge" which will maintain traffic during the week while work progresses underneath.
 
2/6/2019Utility work is underway at the Old Mill Stream Branch location. Temporary concrete barrier has been placed at the Gravel Run bridge in advance of demolition work which will commence in March.
 
1/1/2018Engineering underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202