10/31/2019 | The bridge at Old Mill Stream was successfully moved into place. Due to prolonged rain an additional day was needed to complete backfilling and paving. |
10/31/2019 | The bridge at Old Mill Stream was successfully moved into place. Due to prolonged rain an additional day was needed to complete backfilling and paving. |
|
|
8/6/2019 | Attention has shifted to the Old Mill Stream bridge at the south end of town, where crews are constructing the new bridge in the staging area. Construction of the new bridge foundations and abutments is underway - the bulk of this work is accomplished via weekend full road closures and overnight single lane closures. Steel plates across MD 213 cover the excavated bridge abutment areas and maintain traffic most of the time while giving workers needed access during overnight hours and weekend closure periods. The second of four planned weekend closures at this location should occur in mid-August. On the north end of town work continues at the Gravel Run bridge as crews are forming the wing walls in preparation for the last major concrete pours. One more weekend closure is needed at Gravel Run; this date has not yet been determined. |
|
|
4/1/2019 | MD 213 CLOSURE UPDATE Please see the closure/detour map on the "Maps" tab of this project website.
The first of four planned weekend MD 213 closures at Gravel Run will begin Friday, April 5 at 7 p.m. and continue through the weekend. MD 213 will reopen by 5 a.m. Monday morning, April 8. Detour signs will be posted. Commercial truck drivers passing through Centreville over the weekend may want to avoid using MD 304/Water Street in town due to limited turning radius. Stay on US 301 if possible.
Crews will use this closure to install a temporary "jump bridge" which will maintain traffic during the week while work progresses underneath. |
|
|
1/1/2018 | Engineering underway. |
|
No events found at this time. |