County:Prince George's Project Number:PG127_52
IS 0095 CAPITAL BELTWAY BRIDGE 1615305, 1615306 ON I-495/95 OVER MD 214
Status
12/12/2018Work zone pavement marking work has begun.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Underway 2018
Right-of-Way
Construction Fall 2018 Fall 2021
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
12/12/2018Work zone pavement marking work has begun.
 
11/7/2018PROJECT DESCRIPTION

This project, located in Prince George’s County, is for the replacement of the existing dual bridge
on I-95/I-495(Capital Beltway) over MD 214 (Central Avenue), and the barrier of a box culvert
on I-95/I-495 over the Southwest branch of Western branch of Patuxent Creek. This project also
extends the westbound left turn lanes MD 214 (Central Avenue) to five (5) lanes under the bridge
and adds a shoulder on the eastbound lane between the MD 214 ramps.
The work will consist of the following:

(a) Removal and replacement of dual Bridge Nos.1615305 and 1615306 on I-95/I-495
(Capital Beltway) over MD 214 (Central Avenue)

(b) Removal and replacement of traffic barrier for dual Concrete Box Culvert Nos.
1615605 and 1615606 carrying Southwest Branch of Western Branch Patuxent
River

(c) Widening of the westbound traffic lanes on MD 214 from four (4) to five (5) at the
bridge and adding a shoulder to the eastbound traffic lane

(d) Roadway reconstruction on the approaches of the bridge

(e) Installation of 54-inch water main with 78-inch steel casing

(f) Removal of existing traffic barrier W-beam

(g) Installation of traffic barrier W-beam

(h) Installation of concrete median traffic barrier

(i) Installation of curb and gutter(j) Milling and resurfacing of existing pavement(k) Installation of permanent pavement markings, signing, lighting, ITS, and traffic signalmodifications(l) Installation of storm drain systems and storm water management facilities(m) Maintenance of traffic and erosion and sediment control as required to perform theproposed improvements
 
1/1/2016Engineering underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202