Home
Business Center
Projects & Studies
Commuter & Travel
Safety Programs
Environment & Community
Info Center
State Highway Administration
business center
Projects & Studies
commuter & travel
safety programs
environment & Community
information center
contact us

Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Montgomery Project Number:MO580_51
CO 7073 SEMINARY ROAD BRIDGE 1512900 OVER I-495
Status
9/4/2018Anchor Construction is working on removing and hauling trees cut by PEPCO for utility relocation.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way
Construction Fall 2017 Summer 2020
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
9/4/2018Anchor Construction is working on removing and hauling trees cut by PEPCO for utility relocation.
 
8/13/2018This month, crews will work on reconstructing the traffic barrier at the piers.

For more information about this project, please contact MDOT SHA Project Engineer Yassin Ahmed at Yahmed@sha.state.md.us

 
7/2/2018This summer, crews are awaiting delivery of bearing plates and before they begin the erection of structural steel. In the meantime, the project engineering team also awaits final design changes to traffic barriers for Pier #1 and Pier #3.

For more information about this project, please contact MDOT SHA Project Engineer, Mr. Mustapha Corr, at mcorr@sha.state.md.us or MDOT SHA District 3 Area Engineer, Mr. Bill Kucharek, t bkucharek@sha.state.md.us
 
6/4/2018The contractor is waiting on the delivery of bearing plates and will then begin erection of structural steel.

For more information about this project, please contact Mr. Yassin Ahmed, MDOT SHA Project Engineer, at yhmed@sha.state.md.us .
 
5/2/2018Bridge concrete, substructure and pier work continues this May.

For more information about this project, please contact MDOT SHA Project Engineer, Mr. Mustapha Corr, at mcorr@sha.state.md.us or MDOT SHA District 3 Area Engineer, Mr. Bill Kucharek, t bkucharek@sha.state.md.us
 
4/16/2018Work continues this April on removal portion of existing superstructure and substructure for stage 1 construction, and substructure concrete repairs.
 
4/3/2018Demolition work and substructure concrete repairs continue this April on this bridge rehabilitation project which is now 33 percent complete. Progress permitting, the entire project should be complete by year end 2018. For more information about this project, please contact MDOT SHA Project Engineer, Mr. Mustapha Corr, at mcorr@sha.state.md.us or MDOT SHA District 3 Area Engineer, Mr. Bill Kucharek, t bkucharek@sha.state.md.us
 
3/2/2018Demolition work on the project continues this winter. Intermittent lane closures on Seminary Road and I-495 are possible weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 8 p.m. to 5 a.m. Additional work times and lane closures may be necessary to expedite various phases of work and keep the project on schedule. For more information on this project, please contact Mr. Mustapha Corr, MDOT SHA Project Engineer, at mcorr@sha.state.md.us or Mr. Bill Kucharek, MDOT SHA District 3 Area Engineer, at bkucharek@sha.state.md.us
 
1/23/2018Demolition work on the bridge continues this winter. The project is now seven percent complete and the estimated completion date for the project is the end of 2018.

Possible intermittent lane closures through the end of the project include:

• Inner and outer loops of I-495 (Capital Beltway) from MD 97 (Georgia Avenue, exit 31) to MD 185 (Connecticut Avenue, exit 33). Intermittent single and double left and right lane closures, overnight, Sunday through Thursday, between 9 p.m. to 5 a.m.

Additionally, crews are also permitted to close:

• Seminary Road from Hale Street to MD 192 (Forest Glen Road). Intermittent left and right single northbound and southbound lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 10 p.m. to 5 a.m.

Equipment used for construction may be disruptive. Although traffic volumes will be significantly less during off-peak and overnight lane closure times, motorists are encouraged to allow for additional travel time and seek alternate routes.

Drivers can also know before they go by calling 1-855-466-3511 or visiting www.md511.org for live traffic updates.

For more information about this project, please contact Mr. Mustapha Corr, MDOT SHA District 3 Project Engineer at mcorr@sha.state.md.us , 443-452-7565, or Mr. Bill Kucharek, MDOT SHA District 3 Area Engineer, at bkucharek@sha.state.md.us , 301-513-7452.
 
12/14/2017The Maryland Department of Transportation State Highway Administration (MDOT SHA) is rehabilitating the Seminary Road Bridge over I-495 (Capital Beltway) in Montgomery County.

The $6.2 million project begins this fall and is expected to be complete by the end of 2018. Beginning this January, crews will begin overnight demolition of the bridge wall (parapet).

The work must be performed at night for the safety of the traveling public on I-495 directly beneath the bridge wall. To complete the bridge demolition work, crews are permitted to close the following lanes:

• Inner and outer loops of I-495 (Capital Beltway) from MD 97 (Georgia Avenue, exit 31) to MD 185 (Connecticut Avenue, exit 33). Intermittent single and double left and right lane closures, overnight, Sunday through Thursday, between 9 p.m. to 5 a.m.

Additionally, crews are also permitted to close:
• Seminary Road from Hale Street to MD 192 (Forest Glen Road). Intermittent left and right single northbound and southbound lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 10 p.m. to 5 a.m.

Equipment used for construction may be disruptive. Although traffic volumes will be significantly less during off-peak and overnight lane closure times, motorists are encouraged to allow for additional travel time and seek alternate routes.

Drivers can also know before they go by calling 1-855-466-3511 or visiting www.md511.org for live traffic updates.

For more information about this project, please contact Mr. Mustapha Corr, MDOT SHA District 3 Project Engineer at mcorr@sha.state.md.us , 443-452-7565, or Mr. Bill Kucharek, MDOT SHA District 3 Area Engineer, at bkucharek@sha.state.md.us , 301-513-7452.
 
12/4/2017installation of the bridge protection shield above the Capital Beltway as does telecommunications-related relocation work for the project.

The project is now seven percent complete. The entire project should be complete by the end of 2018.

For more information about this project, please contact MDOT SHA Project Engineer Mustapha Corr at mcorr@sha.state.md.us or MDOT SHA District 3 Area Engineer Bill Kucharek at bkucharek@sha.state.md.us.
 
10/23/2017BRIDGE DEMOLITION WORK BEGINS THIS OCTOBER

The Maryland Department of Transportation State Highway Administration (MDOT SHA) is rehabilitating the Seminary Road Bridge over I-495 (Capital Beltway) in Montgomery County. The $6.2 million project begins this fall and is expected to be complete by the end of 2018. Beginning this month, crews will begin demolition of the bridge’s deck (driving surface) to prepare for construction of a new driving surface.

MDOT SHA’s contractor, Anchor Construction Corporation of Washington, D.C., will shift traffic to one side of the bridge and work on the other side. Crews will control traffic throughout the project.

Two lanes of traffic – one in each direction – will be maintained on the bridge during the rehabilitation, but crews are permitted to close a single lane on Seminary Road Mondays through Fridays between 9 a.m. and 3 p.m. and Sunday nights through Friday mornings between 11 p.m. and 5 a.m. On the Capital Beltway, crews are permitted to close multiple lanes, including brief total closure of all traffic lanes during steel beam removal and replacement Sunday nights through Friday mornings between 11 p.m. until 5 a.m.

Equipment used for construction may be disruptive. Approximately 224,000 vehicles travel on this section of I-495 each day, and nearly 38,000 vehicles travel on Seminary Road.

Although traffic volumes will be significantly less during off-peak and overnight hours, motorists are encouraged to allow for additional travel time and seek alternate routes.

Stay alert and look for reduced speed limits, narrow driving lanes and highway workers. Slow down, and don’t follow too closely. Work Zone Safety is in Your Hands.

Maryland drivers can also know before they go by calling 1-855-466-3511 or visiting www.md511.org for live traffic updates. For more information about this project, please contact Mr. Mustapha Corr, MDOT SHA District 3 Project Engineer at 443-452-7565, or Mr. Bill Kucharek, MDOT SHA District 4 Area Engineer, at 301-513-7452.
 
10/5/2017HOGAN ADMINISTRATION ANNOUNCES SEMINARY ROAD BRIDGE REHABILITATION OVER I-495 IN SILVER SPRING

Project will Eliminate Another Structurally Deficient Bridge

(October 5, 2017) – The Hogan Administration today announced the Maryland Department of Transportation State Highway Administration (MDOT SHA) is rehabilitating the Seminary Road Bridge over I-495 (Capital Beltway) in Montgomery County. The $6.2 million project will begin this week and is expected to be complete by the end of 2018.

Under Governor Larry Hogan’s leadership, Maryland is making record investments in highways and bridges. Of the 69 structurally deficient bridges identified in June 2015 by the Hogan Administration, 41 have been rehabilitated or replaced and are no longer structurally deficient. The remaining 28 are in various stages of design and are actively moving toward construction or repair.

Constructed in 1964, the bridge is safe for the traveling public but requires rehabilitation. Crews will replace the steel beams and the deck (driving surface) of the bridge. Local utility service providers will work with MDOT SHA’s contractor to relocate utilities during the bridge rehabilitation project.

MDOT SHA’s contractor, Anchor Construction Corporation of Washington, D.C., will shift traffic to one side of the bridge and work on the other side. Crews will control traffic throughout the project.

In addition to replacing the bridge beams and driving surface, crews will apply a protective fiber wrap to the bridge pier columns, protecting the concrete and steel from weather elements. MDOT SHA will resurface the Seminary Road bridge approaches, as well as the inner and outer loops of I-495 in the project area.

Two lanes of traffic – one in each direction – will be maintained on the bridge during the rehabilitation, but crews are permitted to close a single lane on Seminary Road Mondays through Fridays between 9 a.m. and 3 p.m. and Sunday nights through Friday mornings between 11 p.m. and 5 a.m. On the Capital Beltway, crews are permitted to close multiple lanes, including brief total closures during steel beam removal and replacement Sunday nights through Friday mornings between 11 p.m. until 5 a.m.

MDOT SHA had planned to close the bridge and detour traffic completely, but determined after meeting with community leaders that maintaining traffic during construction better served area residents. Community input was vital in the planning of this project.

Equipment used for construction may be disruptive. Approximately 224,000 vehicles travel on this section of I-495 each day, and nearly 38,000 travel on Seminary Road. Although traffic volumes will be significantly less during off-peak and overnight hours, motorists are encouraged to allow for additional travel time and seek alternate routes.

Stay alert and look for reduced speed limits, narrow driving lanes and highway workers. Slow down, and don’t follow too closely. Work Zone Safety is in Your Hands. Maryland drivers can also know before they go by calling 511 or visiting www.md511.org for live traffic updates.





 
1/1/2016Engineering underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202