Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Howard Project Number:HO756_23
MD 0032 SYKESVILLE ROAD LINDEN CHURCH ROAD TO I-70
Status
4/5/2017A noise study is currently being completed to determine which properties will be impacted by the widening of MD 32 and where mitigation is reasonable and feasible to abate the impact. The study is anticipated to be complete by the end of Spring 2017.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning Complete
Engineering Underway 2019
Right-of-Way Underway 2022
Construction 2019 2022
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic: Summer 2021
 
Status Updates
 
4/5/2017A noise study is currently being completed to determine which properties will be impacted by the widening of MD 32 and where mitigation is reasonable and feasible to abate the impact. The study is anticipated to be complete by the end of Spring 2017.
 
3/6/2017The project is currently at the concept development stage.
 
3/5/2017The noise study for the corridor is complete. The study determined that no communities along MD 32 from Linden Church Road to I-70 meet the reasonable and feasible criteria as required by the MDOT SHA Noise Policy. For more information on the Noise Policy, please visit: http://roads.maryland.gov/index.aspx?PageId=322

The project is progressing through the concept development phase and is beginning the preparation of contract documents. This project is being delivered using the Design-Build methodology, with contract procurement beginning in early 2018. For more information concerning the project timeline, please visit: http://www.roads.maryland.gov/Pages/Dsbinfo.aspx?PageId=873
 
1/4/2017The project proposes to improve MD 32 from a two lane highway to a four lane divided highway from Linden Church Road to I-70, a distance of approximately 7.0 miles. The scope of improvements is anticipated to include, but not limited to, earthwork, new pavement construction, existing pavement rehabilitation, drainage, stormwater management, erosion & sediment control, reforestation, landscaping, intersection improvement, signing and marking, lighting, structures, utility coordination, and environmental permit acquisition. The proposed roadway on MD 32 will generally be a 4 lane divided highway with 12 foot lanes, 4 foot paved inside shoulders, 10 foot paved outside shoulders, and a 26 foot grass median with traffic barrier protection. This project is actively under concept development.
 
8/1/2016The MD 32 from Linden Church Road to I-70 project is fully funded for design, right-of-way acquisition and construction as a Design Build project. The project is currently at the early concept development stage.
 
1/1/2013Engineering underway.
 


Events

   Informational Public Workshop

Date:

10/17/2017
Location:14025 Burntwoods Road, Glenelg ,MD 21737
 
   Informational Public Workshop

Date:

6/28/2017
Location:4691 Ten Oaks Road, Dayton ,MD 21036
 
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202