Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Howard Project Number:HO488_51
IS 0095 NB SRI - MONTGOMERY ROAD OVERPASS TO I-895 INTERCHANGE
Status
12/21/2017The project is 97% complete. Crews are finishing drainage installation and completing landscaping.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way
Construction Fall 2015 Summer 2018
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
12/21/2017The project is 97% complete. Crews are finishing drainage installation and completing landscaping.
 
11/20/2017The project is 92% complete. All sound wall has been placed.

Recently completed work:
All posts and panels have been set for the wall and 2/3 of the wall has been stained.

Current work items/areas:
Finish staining the panels and grade for drainage.

Upcoming work items/areas over the next month:
Finish drainage and staining and start landscaping.
 
9/26/2017The project is 85% complete. Crews continue to set panels and place drainage within the project limits.
 
5/22/2017The project is 54% complete. All the caissons (footers) have been installed, 296 of 452 posts set for the wall. Crews will continue to install posts and then begin placing the wall.
 
3/24/2017Crews continue to install caissons (footers or bases). Currently, 393 of the 452 caissons have been placed while 181 posts are set to hold the wall panels. Crews are preparing to place sound wall in the coming month, weather permitting.
 
2/23/2017Crews continue to install caissons (footers or bases). Currently, 373 of the 452 caissons have been placed while 137 posts are set to hold the wall panels. Weather permitting, crews will begin placing the wall panels this spring.
 
12/20/2016Recently completed work (since last newsletter)
-274 of 452 caissons (footers) completed, first 80 posts set for the wall

Current work items/areas:
-Continuing to drill shafts for the caissons (footers) north of Montgomery Rd. and set posts

Upcoming work items/areas over the next month:
-Continuing to drill and pour concrete for the caissons and set posts for the wall.
-Wall panels will be placed this winter, weather permitting

 
11/21/2016Recently completed work:
-256 of 452 caissons (footers) completed, first 45 posts set for the wall.

Current work items/areas:
-Continuing to drill shafts for the caissons (footers) north of Montgomery Rd. and crews continue to set posts

Upcoming work items/areas over the next month:
-Continuing to drill and pour concrete for the caissons and set posts for the wall.
-Panels for the sound wall will begin to be placed in December 2016, starting closest to Montgomery Road and moving towards I-895.


 
10/17/2016Recently completed work (since last newsletter)
-248 of 452 caissons (footer) completed, first 15 posts set for the wall

Current work items/areas:
-Continuing to drill shafts for the caissons (footers) north of Montgomery Rd. and set posts

Upcoming work items/areas over the next month:
-Continuing to drill and pour concrete for the caissons and set posts for the wall.
 
9/15/2016Recently completed work (since last newsletter)
-218 of 452 caissons (footer) completed

Current work items/areas:
-Continuing to drill shafts for the caissons (footers) north of Montgomery Rd.

Upcoming work items/areas over the next month:
-Continuing to drill and pour concrete for the caissons and begin to erect the posts in Sept.
 
8/18/2016Recently completed work (since last newsletter)
-159 of 452 caissons (concrete footer) completed

Current work items/areas:
-Continuing to drill shafts (large holes) for the caissons (footers) north of Montgomery Rd.

Upcoming work items/areas over the next month:
-Continuing to drill and pour concrete for the caissons and begin to erect the sound wall in September
 
7/20/2016Recently completed work (since last newsletter)
-85 of 452 caissons (footer) completed

Current work items/areas:
-Continuing to drill shafts for the caissons (footers) North of Montgomery Rd.

Upcoming work items/areas over the next month:
-Continuing to drill and pour concrete for the caissons and begin to erect the sound wall in Sept.
 
7/7/2016As of July 7th, 70 caissons (sound wall footers) have been placed and are ready to receive posts and then walls. Clearing continues for additional caissons and posts.

Citizens are urged to slow down and stay alert in the work zone.
 
12/28/2015Preliminary project work is underway for the $13.6 million sound wall project. Construction limits extend from the Montgomery Road overpass to the I-895 interchange. Area residents are asked to remain alert for work crews.
 
1/1/2013Engineering underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202