Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Garrett Project Number:GA646_52
US 0219 IHB - I-68 TO OLD SALISBURY ROAD
Status
6/7/2019This project is at 20% completion with a total completion of December of 2020.

The recent work that has been completed in the past month includes;

Installation of E&S controls, excavation and fill, began storm drain system installation

The work currently underway includes;

Storm drain system and earthwork

At this time all work is outside of the traveled roadway and will not impact drivers
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning Complete
Engineering Complete
Right-of-Way Underway 2021
Construction Winter 2018 Summer 2021
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
6/7/2019This project is at 20% completion with a total completion of December of 2020.

The recent work that has been completed in the past month includes;

Installation of E&S controls, excavation and fill, began storm drain system installation

The work currently underway includes;

Storm drain system and earthwork

At this time all work is outside of the traveled roadway and will not impact drivers
 
6/7/2019This project is at 20% completion with a total completion of December of 2020.

The recent work that has been completed in the past month includes;

Installation of E&S controls, excavation and fill, began storm drain system installation

The work currently underway includes;

Storm drain system and earthwork

At this time all work is outside of the traveled roadway and will not impact drivers
 
6/7/2019This project is at 73% completed with an estimated completion date of summer of 2020.

The work accomplished last week includes;

Re-mobilization of event #16

Bridge 21077: Poured stage #2 DB bridge deck. Installing rebar Stage #2 NB bridge deck

Bridge 20178: Completed pour of NB Stage #1 wall. Footer pour for single face barrier approach in WV. Form and pour abutment A Stage #2 footer. Continue demo of Pier #1 SB Stage #2 Pier Cap

Begin Paving 19 mm asphalt for Stage #2 traffic switch NB in WV

Upcoming work includes;

Bridge 21078: Form approach slab #1A SB on MD 63/68 taken for stage 2 construction. Form wingwall V11. Setting temporary bridge across river

Bridge 21077: Pour stage #2 NB bridge deck

Maintain traffic control devices throughout project

Full depth shoulder widening Stage 1A SB. Traffic switch NB

The right lane on both EB and WB on MD 63/68 taken for stage 2 construction. Long term and continuous

Upcoming milestones will be the North bound switch
 
6/7/2019This project is at 73% completed with an estimated completion date of summer of 2020.

The work accomplished last week includes;

Re-mobilization of event #16

Bridge 21077: Poured stage #2 DB bridge deck. Installing rebar Stage #2 NB bridge deck

Bridge 20178: Completed pour of NB Stage #1 wall. Footer pour for single face barrier approach in WV. Form and pour abutment A Stage #2 footer. Continue demo of Pier #1 SB Stage #2 Pier Cap

Begin Paving 19 mm asphalt for Stage #2 traffic switch NB in WV

Upcoming work includes;

Bridge 21078: Form approach slab #1A SB on MD 63/68 taken for stage 2 construction. Form wingwall V11. Setting temporary bridge across river

Bridge 21077: Pour stage #2 NB bridge deck

Maintain traffic control devices throughout project

Full depth shoulder widening Stage 1A SB. Traffic switch NB

The right lane on both EB and WB on MD 63/68 taken for stage 2 construction. Long term and continuous

Upcoming milestones will be the North bound switch
 
4/4/2019This project is currently 22% complete.

Current Work:
Installing new drainage structures and pipes.
Stripping topsoil.

Upcoming Work:
Begin work on new bridge over US 40.
 
1/14/2019This project is currently 18% Complete

Current Work:
Work continuing through winter as weather allows.
Installing E&S controls, clearing and grubbing, and grading.
 
10/25/2018This project is currently 15% Complete

Current Work:

Groundbreaking held on October 13, 2018.
Competed utility relocations.
Installing Erosion & Sediment (E & S) Controls.

Upcoming Work:

Continue installation of E & S Controls.
 
10/23/2018MDOT's State Highway Administration officially broke ground for the US219 Realignment project on Saturday, October 13, 2018 in Garrett County.

As crews advance the construction phase, area travelers are advised to remain alert for construction equipment and workers entering and exiting the work zone.

 
7/16/2018This project is currently 12% complete.

Current Work:
This Design/Build contract is still in the design phase.
Work by the contractor has not begun.
 
4/10/2018They are currently in the design phase. They recently completed tree clearing. With this being a design build project the Notice to proceed and contract start date are actually referring to the start of the Design Build Team’s design phase with actual construction anticipated to begin during August 2018
 
1/1/2016Planning underway. Engineering and Right-of-Way to begin during current fiscal year. Construction and Right-of-Way is being funded wiith Appalachian Development Highway System funds.
 
1/1/2001The US 219 design build project was awarded to Triton Construction, Inc. of St. Albans, WV
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202