Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Garrett Project Number:GA197_21
MD 0039 HUTTON ROAD IHB - BRIDGE 1100200 OVER YOUGHIOGHENY RIVER (STAGE 2)
Status
8/24/2018Stage I of this project has been bid and will be under construction in the fall, 2108. Stage 1 involves the construction of a storm water management facility and the relocation of a public sewer service line that is necessary in order to allow for the future bridge replacement project. Stage 2 of the project will be advertised in the fall, 2019 and includes the construction of the bridge and all associated roadway construction. We are currently completing plans for the stage 2 construction and acquiring the required permits.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Underway 2020
Right-of-Way
Construction 2020 2022
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
8/24/2018Stage I of this project has been bid and will be under construction in the fall, 2108. Stage 1 involves the construction of a storm water management facility and the relocation of a public sewer service line that is necessary in order to allow for the future bridge replacement project. Stage 2 of the project will be advertised in the fall, 2019 and includes the construction of the bridge and all associated roadway construction. We are currently completing plans for the stage 2 construction and acquiring the required permits.
 
5/21/2018Stage I of this project is being prepared for construction bids in June of this year. Stage 1 involves the construction of a storm water management facility and the relocation of a public sewer service line that is necessary in order to allow for the future bridge replacement project, which will be included in stage 2 that will be advertised for bids at a later date.
 
2/12/2018Stage I of this project is on schedule to advertise for public bids in June of this year. Stage 1 involves the construction of a storm water management facility and the relocation of a public sewer service line that is necessary in order to allow for the future bridge replacement project, which will be included in stage 2 that will be advertised for bids at a later date.
 
11/7/2017Project Development is continuing with final design plans and environmental permitting.
 
7/26/2017Project Development is continuing with design plans to address storm water management and sediment control during construction. These plans are currently being reviewed by the appropriate permitting agencies. In addition, soil borings are being completed in the field to aid in the final design of storm water management facilities and bridge foundations.
 
5/12/2017We have completed development of preliminary design plans. Project Development is continuing with conceptual plans to address storm water management and sediment control during construction. These plans are currently being reviewed by the appropriate permitting agencies.
 
2/24/2017SHA is completing development of preliminary design plans, and continues with development of conceptual plans to address storm water management and sediment control during construction. These plans are currently being reviewed by the appropriate permitting agencies.
 
11/16/2016SHA is completing development of preliminary design plans relocating the new bridge to the downstream side of the existing structure. This design has been developed based on an assessment of impacts to utilities, right of way, and wetlands. Conceptual plans to address storm water management and sediment control during construction are currently being reviewed by the appropriate permitting agencies.
 
8/11/2016SHA has developed a preference for relocating the new bridge to the downstream side of the existing structure. This preference was developed based on an assessment of impacts to utilities, right of way and wetlands. We are developing conceptual plans to address storm water management and sediment control during construction.
 
1/21/2016We are evaluating alternative alignments (either side of the existing bridge) that will allow us to construct a new bridge across the Youghiogheny while maintaining traffic on the existing road and bridge. Once construction is complete, we anticipate removing the existing road and bridge. Our goal is to minimize impacts and tie into the current alignment as quickly as possible. Closing MD 39 and detouring traffic to other roads in the area was not a good solution for this crossing.
 
7/28/2015Engineering underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202