Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR580_11
IS 0070 BALTIMORE NATIONAL PIKE AT MEADOW ROAD - IJAMSVILLE ROAD INTERCHANGE STUDY
Status
8/22/2017Design of westbound I-70/Ijamsville ramp is underway under a Maryland Department of Highway State Highway Administration (MDOT/SHA) District 7 Access permit. The project is being undertaken by a developer to improve I-70 access as a condition for receiving County approval of private development projects planned in the immediate area. The MDOT/SHA District 7 office is responsible for final approval of the access permit prior to initiation of highway construction. Design and future construction is to be funded by the developer up front, and guaranteed by a County Transportation Infrastructure Financing (TIF) guarantee. The new eastbound off-ramp would be constructed under the same permitting and funding arrangement in the near future.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning Complete
Engineering Underway Pending
Right-of-Way
Construction
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
8/22/2017Design of westbound I-70/Ijamsville ramp is underway under a Maryland Department of Highway State Highway Administration (MDOT/SHA) District 7 Access permit. The project is being undertaken by a developer to improve I-70 access as a condition for receiving County approval of private development projects planned in the immediate area. The MDOT/SHA District 7 office is responsible for final approval of the access permit prior to initiation of highway construction. Design and future construction is to be funded by the developer up front, and guaranteed by a County Transportation Infrastructure Financing (TIF) guarantee. The new eastbound off-ramp would be constructed under the same permitting and funding arrangement in the near future.
 
2/21/2014Partial Planning funding has been removed and this project is on hold until funding becomes available.
 
12/13/2013Partial Planning funding has been removed and this project is on hold until funding becomes available.
 
10/3/2013Partial Planning funding has been removed and this project is on hold until funding becomes available.

 
11/19/2008A full team Project Scoping Meeting and an Agency Field Review were held in the Fall of 2007.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202