Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR571_51
US 0015 CATOCTIN MOUNTAIN HIGHWAY SRI - MONOCACY BOULEVARD INTERCHANGE
Status
6/9/2017-Christopher Crossing, Monocacy Blvd, US 15 SB Exit ramp and the US 15 NB Entrance ramps will open to traffic Fall 2017
-US 15 SB Entrance ramp and NB Entrance ramp will open to traffic Spring 2018
-Project Completion 7Summer 2018
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning Complete
Engineering Complete
Right-of-Way Complete
Construction Spring 2015 Spring 2018
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
6/9/2017-Christopher Crossing, Monocacy Blvd, US 15 SB Exit ramp and the US 15 NB Entrance ramps will open to traffic Fall 2017
-US 15 SB Entrance ramp and NB Entrance ramp will open to traffic Spring 2018
-Project Completion 7Summer 2018
 
5/24/2017Current work items/areas:
• Continued compaction of fill areas for Monocacy Interchange
• US 15 NB and SB Reconstruction of Tuscarora Bridge
• Continued installation of Signals, Light poles and Foundations (Cable and Conduit)
• Excavation of Bio-Retention Ponds for Storm Water Management
• Pulling Electrical lines through underground conduit
• Placing Guardrail
• Deck pours on the new Monocacy Bridge over US 15

Upcoming work items/areas over the next month:
• Placing Topsoil and stabilizing various areas
• Installing Curb and Gutter
• Building Bio-Retention Ponds for Storm Water Management
• Continued pouring of the deck of new Monocacy Bridge over US 15
• Continued installation of Underdrain along roadways
• Preparing subgrade for the Park and Ride lot
• Continued reconstruction of US 15 NB and SB Tuscarora Bridge
 
4/19/2017Current work items/areas:
• Continued compaction of fill areas for Monocacy Interchange
• US 15 NB and SB Reconstruction of Tuscarora Bridge
• Installation of Underdrain along roadways
• Installation of Signals, Light poles and Foundations (Cable and Conduit)
• Excavation of Bio-Retention Ponds for Storm Water Management
• Base-Paving on US 15 NB Exit Ramp
• Placing Guardrail

Upcoming work items/areas over the next month:
• Placing Topsoil and stabilizing various areas
• Placing Guardrail
• Pulling Electrical lines through underground conduit
• Base-Paving US 15 NB Entrance Ramp, Christopher Crossing Tie-in and Thomas Johnson Tie-in
• Pour deck of new Monocacy Bridge over US 15
 
3/16/2017Recent work:
• Reconstruction of Biggs Ford Road crossover accel/decel lanes are 98% complete
• Paving on Christopher Crossing 85% complete
• Paving on US 15 NB entrance and exit ramps 85% complete
• Paving on Thomas Johnson Drive tie in, 65% complete
• Paving on new Monocacy Blvd 75% complete
• Paving on US 15 SB entrance and exit ramps 75% complete
• Installation and tie in to existing sewer line 100% complete
• Installation and tie in of electrical line 90% complete

Upcoming work items/areas over the next month:

• Placing Topsoil and stabilizing various areas
• Placing Guardrail
• Pulling Electrical lines through underground conduit

 
2/16/2017Recently completed work:
• Reconstruction of Biggs Ford Road crossover accel/decel lanes are 98% complete
• Paving on Christopher Crossing 85% complete
• Paving on US 15 NB entrance and exit ramps 85% complete
• Paving on Thomas Johnson Drive tie in, 65% complete
• Paving on new Monocacy Blvd 75% complete
• Paving on US 15 SB entrance and exit ramps 75% complete
• Installation and tie in to existing sewer line 100% complete
• Installation and tie in of electrical line 90% complete

Current work items/areas:
• US 15 NB and SB Reconstruction of Tuscarora Bridge
• Installation of Underdrain along roadways
• Installation of Signals, Light poles and Foundations (Cable and Conduit)
• Excavation of Bio-Retention Ponds for Storm Water Management

Upcoming work items/areas over the next month:
• Placing Topsoil and stabilizing various areas
• Placing Guardrail
• Pulling Electrical lines through underground conduit
• Placing GAB on the US 15 NB Exit Ramp
 
1/18/2017Crews will be active throughout the winter.

Current work items and areas:
• Reconstruction of Biggs Ford Road crossover accel/decel lanes are 95% complete. Pavement markings are scheduled to be installed.
• Paving on Christopher Crossing 85% complete
• Paving on US 15 NB entrance and exit ramps 85% complete
• Paving on Thomas Johnson Drive tie in, 60% complete
• Paving on new Monocacy Blvd 75% complete
• Paving on US 15 SB entrance and exit ramps 75% complete
• Continued compaction of fill areas for Monocacy Interchange
• US 15 NB and SB Reconstruction of Tuscarora Bridge
• Installing Underdrain along roadways
• Installation of Signals, Light poles and Foundations (Cable and Conduit)
• Excavating Bio-retention Ponds for Storm Water Management


 
12/23/2016On 12/22/16 crews re-opened the US 15 crossover at Biggs Ford Road. Crews will continue to work on the US 15 at Monocacy Boulevard interchange throughout the winter season.
 
12/15/2016Recently completed work:
•Monocacy Blvd. Bridge Deck Pan Installation is 100% complete
•Waterline Installation is 100% complete
•Drainage structure are 100% complete

Current work items/areas:
•Continued placing and compacting of fill areas for Monocacy Interchange
•US 15 NB reconstruction of Tuscarora Bridge
•Installing Drainage Pipe/Underdrain
•Paving on Christopher’s Crossing, US 15 SB Entrance and Exit Ramps and Thomas Johnson Drive
•Excavating Bio-retention Ponds for Storm Water Management
•Reconstruction of Biggs Ford Road deceleration lane and acceleration lane US 15 SB

 
11/21/2016Recently completed work:
• Monocacy Blvd. bridge structural steel is 100 % in place.

Current work items/areas:
• US 15 NB reconstruction of Tuscarora Bridge
• Installing Drainage Pipe/Underdrain & Structures
• Grading at Christopher Crossing and Thomas Johnson Drive
• Installing Curb and Gutter on Monocacy Blvd.
• Excavating Bio-retention Ponds for Storm Water Management
• Reconstruction of Biggs Ford Road deceleration lane and acceleration lane
• Deck pan placement and welding on New Monocacy Bridge over US 15 (Night work)
• Installing Water lines
• Paving

Upcoming work items/areas over the next month:
• Installing Drainage Pipe/Underdrain
• Installing Drainage Structures
• Installing Water lines
• Paving
 
10/17/2016Recently completed work (since last newsletter):
•Monocacy Blvd. Bridge Structural Steel Erection (placement) is 90% complete


Current work items/areas:
•US 15 NB reconstruction of Tuscarora Bridge
•Installing Drainage Pipe/Underdrain
•Placing and Fine Grading GAB on Christopher Crossing and Thomas Johnson Drive
•Installing Curb and Gutter on Christopher Crossing and Thomas Johnson Drive
•Excavating Bio-retention Ponds for Storm Water Management
•Reconstruction of Biggs Ford Road deceleration lane and exceleration lane is underway
•Structural Steel Erection on New Monocacy Bridge over US 15 will continue at night.




Upcoming work items/areas over the next month:
• Working on drainage within the project limits
•Relocating Power lines
•Installing Water lines
•Paving
 
9/15/2016Recently completed work (since last newsletter):
•Monocacy Blvd. Bridge Abutment B is 100% complete
•Monocacy Blvd. Bridge Center Pier is 100% complete

Current work items/areas:
•Continued placing and compacting of fill areas for Monocacy Interchange
•US 15 NB reconstruction of Tuscarora Bridge
•Installing Drainage Pipe & Structures
•Placing and Fine Grading GAB on Christopher Crossing and Thomas Johnson Drive
•Installing Curb and Gutter on Christopher Crossing and Thomas Johnson Drive
•Excavating Bio-retention Ponds for Storm Water Management


Upcoming work items/areas over the next month:
•Installing Drainage Pipe/Underdrain
•Installing Drainage Structures
•Structural Steel Erection on New Monocacy Bridge over US 15 (Night work)
•Reconstruction of Biggs Ford Road deceleration lane (Night work)
•Relocating Power lines
•Installing Water lines
•Paving/Graded Aggregate Base
 
9/15/2016We have US 15 southbound crossover to Monocacy Blvd. closed due to sight distance issues concerning the temporary concrete barrier wall. Temporary Monocacy Boulevard is operational for traffic heading US 15 northbound to exit onto existing Monocacy Blvd. Beginning September 28th, there will be some temporary lane closures on US 15 (night work) while erecting Structural Steel for the new Monocacy Bridge over US 15 starting on the southbound side.
 
9/15/2016We have US 15 southbound crossover to Monocacy Blvd. closed due to sight distance issues concerning the temporary concrete barrier wall. Temporary Monocacy Boulevard is operational for traffic heading US 15 northbound to exit onto existing Monocacy Blvd. Beginning September 28th, there will be some temporary lane closures on US 15 (night work) while erecting Structural Steel for the new Monocacy Bridge over US 15 starting on the southbound side.
 
8/15/2016Recently completed work:
•Monocacy Blvd. Bridge Abutment A is 100% complete
•Monocacy Blvd. Bridge Abutment B is 90% complete

Current work items/areas:
•Continuing placing and compacting fill areas for Monocacy Interchange
•Monocacy Blvd. Bridge & Tuscarora Bridge NB
•Installing Drainage Pipe & Structures

Upcoming work items/areas over the next month:
•Installing Drainage Pipe
•Installing Drainage Structures
 
8/2/2016Please be advised that we will be shifting traffic per plan from existing Monocacy Blvd to Temporary Monocacy Blvd on 8/7/16. This switch will stay in place until such time as the new Monocacy Blvd bridge is completed.
 
6/17/2016As of 6/15/16
Recently completed work (since last newsletter):
• Monocacy Blvd. Bridge Abutment A is 100% complete
• Monocacy Blvd. Bridge Abutment B is 75% complete

Current work items/areas:
• Continuing placing and compacting fill areas for Monocacy Interchange
• Monocacy Blvd. Bridge Center Pier Columns
• Installing Drainage Pipe & Structures

Upcoming work items/areas over the next month:
• Installing Drainage Pipe
• Installing Drainage Structures
• Constructing Temp. Monocacy Blvd.
 
6/2/2016Recently completed work:
•Monocacy Blvd. Bridge Abutment A is 100% complete
•Monocacy Blvd. Bridge Abutment B is 75% complete

Current work items/areas:
•Continuing placing and compacting fill areas for Monocacy Interchange
•Monocacy Blvd. Bridge Center Pier Columns
•Installing Drainage Pipe & Structures

Upcoming work items/areas over the next month:
•Installing Drainage Pipe
•Installing Drainage Structures
•Constructing temporary Monocacy Blvd.

Frequently asked questions to add to website:
Q: When will the project be complete?
A: Summer of 2018

Q: How will this project effect my commute?
A: Temporary lane closures with minimal interruption, detour for southbound US 15 to Monocacy Blvd is in place.

We have US 15 south bound crossover to Monocacy Blvd. closed with a detour set up due to sight distance issues due to temporary concrete barrier wall. Also motorists may encounter night time temporary lane closures.
 
2/11/2016Crews are now installing waterlines and storm drains, along with continued construction of the bridge piers.
 
11/4/2015Constructions crews closed the median crossover at southbound US 15 to eastbound Monocacy Boulevard on November 4. Weather permitting; crews will open the crossover early 2016.

The temporary closure is necessary for motorists’ safety as SHA’s contractor will be working behind concrete barrier in the center median, obstructing drivers’ sight distance. Motorists traveling south on US 15 will be directed to the US 15/Motter Avenue Interchange to northbound US 15 to MD 26 (Liberty Road) then back to eastbound Monocacy Boulevard.
 
5/15/2015The contractor was issued Notice to Proceed (NTP) with construction on or before May 15, 2015. The project is now in the construction phase. For updates throughout construction, please see the updates and media tabs. If you would like to be notified by email of updates on this project, please provide your email address using the form under "Feedback" and select "Please add my/our name(s) to the Mailing List."
 
4/14/2015The contract for the project has been awarded to Kibler Construction Co. for the bid amount of $31,564,162.17.
 
1/1/2013Engineering underway. The County is providing $2.0 million to proceed with engineering. The City has also committed $2.0 million for engineering with $1.4 million being deferred to 2015. The cost shown is SHA share only.
 


Events

   Celebration Event

Date:

8/19/2015
Location:1915 Sawmill Court (at the intersection of Christophers Crossing), Frederick ,MD 21702
 
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202