Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR559_51
MD 0355 URBANA PIKE IHB - BRIDGE 1008400 OVER CSX
Status
9/26/2019This project is 57% complete and expected to finish in summer 2020.

The contractor recently poured concrete for wing walls III and IV, and poured the bearing pads to place the steel girders of the new bridge.

Currently, crews are backfilling abutments and adding fill to widen MD 355 to install new sidewalk. The existing piers of the old bridge are being demolished and excavated with CSX overseeing operations.

The contractor plans to start setting steel girders for the new bridge on Thursday, Oct. 3. at 10 p.m. A flagging operation will be in effect in both directions to stop traffic periodically for 15 minutes at a time when moving the girders off tractor trailers. This operation will end at 4 a.m. on Friday, Oct. 4.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2021
Construction Summer 2017 Spring 2020
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
9/26/2019This project is 57% complete and expected to finish in summer 2020.

The contractor recently poured concrete for wing walls III and IV, and poured the bearing pads to place the steel girders of the new bridge.

Currently, crews are backfilling abutments and adding fill to widen MD 355 to install new sidewalk. The existing piers of the old bridge are being demolished and excavated with CSX overseeing operations.

The contractor plans to start setting steel girders for the new bridge on Thursday, Oct. 3. at 10 p.m. A flagging operation will be in effect in both directions to stop traffic periodically for 15 minutes at a time when moving the girders off tractor trailers. This operation will end at 4 a.m. on Friday, Oct. 4.
 
8/23/2019Both abutments, wing walls and pier of the new bridge have been poured with concrete. Abutment B's first footer was poured last week with 81 yards of concrete. Abutment A's footers and wing walls are finished.

Upcoming work includes digging out the second footer for abutment B. It will then be poured along with the two wing walls. Crews will need to strip the forms off the wing walls of abutment A and then backfill.

The contractor expects to set the steel girders for the new bridge in October. This project is estimated to be complete in summer 2020.
 
7/22/2019This project is 52% complete and expected to finish summer 2020.

The contractor recently set forms for abutment A and the cheek walls which are scheduled for a concrete pour on Tuesday, July 23.

Forms have also been set for the wing wall III footer.
 
6/26/2019This project is 50% complete and expected to finish summer 2020.

The contractor has completed the concrete pour for abutment B and the cheek walls. Crew continue to set forms and place steel rebar in preparation for the concrete pour for abutment A and its wing walls.
 
4/10/2019This project is 43% complete and is scheduled for full completion in spring 2020.

Recently, crews installed steel beams on the northside for the new bridge. They are now working on setting forms to install steel rebar before pouring concrete. The crane has been moved to the new bridge’s southside and will use a hammer to drive steel beams into the ground until it reaches solid rock.

MDOT SHA is also currently working with CSX on the demolition of the existing bridge’s pier footers by the railroad tracks.

The work zone will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.
 
3/28/2019This project is currently 43% complete and is scheduled to be fully complete in Spring 2020.

Recently completed work (since last newsletter) :

- Piles on north side complete, moved crane and hammer to south side.

Current work items/areas:

- Maintaining E&S controls
- Existing bridge sub-structure demolition (Pier footers by tracks)
- Pile Driving

Upcoming work items/areas over the next month:

- Maintaining E&S controls
- Form footers to pour concrete

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

Will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.

 
2/28/2019This project is currently 38% complete and is scheduled to be fully complete in Spring 2020.

Current work items/areas:

- Maintaining E&S controls
- Existing bridge sub-structure demolition (Piers by tracks)
- Pile Driving

Upcoming work items/areas over the next month:

- Maintaining E&S controls
- Form footers to pour concrete

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

Will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.
 
1/22/2019This project is currently 35% and is set to be fully complete in Spring 2020.

Recently completed work (since last newsletter):

- Connected temporary waterline to existing waterline

Current work items/areas:

- Installing E&S controls
- Existing bridge sub-structure demolition

Upcoming work items/areas over the next month:

- Installing E&S controls
- Prepare for new sub-structure build

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

Will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.

 
12/18/2018This project is currently 30.5% complete and is scheduled to be fully complete in Fall 2019.

Recently completed work (since last newsletter):

- Connected temporary waterline to existing waterline

Current work items/areas:

- Installing E&S controls
- Existing bridge super-structure demolition

Upcoming work items/areas over the next month:

- Installing E&S controls
- Demolition of existing bridge sub-structure

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

Will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.
 
11/26/2018This project is currently 28% complete and is set to be fully complete in fall 2019.

Recently completed work (since last newsletter):

- Connected temporary waterline to existing waterline

Current work items/areas:
- Installing E&S controls
- Preparing existing bridge for demolition

Upcoming work items/areas over the next month:
- Installing E&S controls
- Begin demolition of existing bridge

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

Will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.
 
10/15/2018This project is currently 26% complete and will be fully complete in Fall 2019.

Recently completed work (since last newsletter):

- Paved temporary roadway

Current work items/areas:

- Backing up shoulders for guardrail placement on temporary roadway

Upcoming work items/areas over the next month:

- Switch traffic onto temporary roadway
- Tie-in temporary waterline to existing waterline
- Installing E&S controls
- Begin demolition of existing bridge

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

Traffic will be shifted to temporary roadway after completion, estimated 10/19/18.
 
9/17/2018This project is currently 23% complete and is set to be fully complete in fall 2019.

Recently completed work (since last newsletter):
- Temporary waterline installed across temporary bridge
Current work items/areas:
- Placing stone for temporary roadway
Upcoming work items/areas over the next month:
- Working on completing stone placement so paving can begin on temporary roadway
- Installing guardrail on temporary roadway

Will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas. Traffic will be shifted to temporary roadway after completion, weather permitting, within the next month.
 
7/19/2018this project is currently 17.6% complete and is on schedule to be fully complete in Fall of 2019.

Recently completed work (since last newsletter)
- Footers for temporary bridge complete
Current work items/areas:
- Receiving materials for temporary bridge assembly.
Upcoming work items/areas over the next month:
- Working on building temporary bridge.

any upcoming work that may be more disruptive than usual:

Will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.
 
6/18/2018This project is currently 15.2% complete and will be fully complete in Fall 2019.

Recently completed work:
-H-piles drilled and placed for temporary bridge

Current work items/areas: -Hauling in fill for temporary roadway, Building temporary MSE wall and shoring supports

Upcoming work items/areas over the next month: -Working on temporary bridge substructure.

Crews will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.
 
5/22/2018This project is currently 14.5% complete and will be finished in Fall 2019

Recently completed work (since last newsletter):
-Drainage structures placed south of tracks.

Current work items/areas:
-Hauling in fill for temporary roadway, Building temporary MSE wall

Upcoming work items/areas over the next month:
-Building temporary roadway and shoring along MD 355 to begin temporary bridge work

We will continue to have flagging operations on MD 355 so trucks hauling materials can safely enter and exit the work areas.
 
4/16/2018Recently completed work (since last newsletter)
-Utility companies have removed all old lines and poles north of bridge.
Current work items/areas:
-Hauling in fill for temporary roadway, Installing drainage structures and pipes
Upcoming work items/areas over the next month:
-Building temporary roadway
The estimated completion date is Fall 2019.
 
1/16/2018Utilities continue to be relocated. Concrete barrier has been placed and crews are preparing for installation of the temporary bridge.
 
12/18/2017Crews continue to move utilities amd place drainage structures for the temporary roadway.
 
11/20/2017Utilities are being relocated and crews are beginning the construction of the temporary roadway.
 
9/13/2017Crews will begin work the week of September 18th
 
1/1/2016Engineering underway. Construction to begin during budget fiscal year.
 


Events

No events found at this time.
 