Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR536_51
MD 0140 TANEYTOWN PIKE BRIDGE 1006200 OVER FLAT RUN
Status
11/13/2017Recently completed work:
-Crews are finalizing the supports for excavation. The stream diversion is in place.

Current work items/areas:
-Crews will move towards demolition of the bridge and complete the second phase of the stream diversion.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2019
Construction Fall 2016 Winter 2019
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
11/13/2017Recently completed work:
-Crews are finalizing the supports for excavation. The stream diversion is in place.

Current work items/areas:
-Crews will move towards demolition of the bridge and complete the second phase of the stream diversion.
 
9/12/2017-Contractor has installed supports in preparation for bridge demo.
-Crews are placing the stream diversion, at this time.
-Once the stream diversion is in place, the existing bridge will be demolished.
 
7/13/2017Recently completed work (since last newsletter)
-Crews installed a temporary pedestrian bridge and pedestrian path for pedestrians to use while work is in progress on the bridge

Current work items/areas:
-Contractor currently working on excavation in preparation for Demo of the existing bridge

 
5/12/2017Recently completed work (since last newsletter)
- Crews completed traffic switch along with MD 140 EB and WB between Silo Hill
Road and Creamery Road

Current work items/areas:
-Finishing installation of the pedestrian path and excavate for the temporary pedestrian bridge abutments

 
2/16/2017Crews have begun to conduct test pitting and installation of rip rap. Drainage pipe and grading has also been started, in preparation of further construction.
 
1/1/2016Engineering underway.
 
1/1/2001Currently, utility are being relocated so that work can begin on the bridge. Utility relocation will continue throughout the winter.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202