Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR536_51
MD 0140 TANEYTOWN PIKE BRIDGE 1006200 OVER FLAT RUN
Status
10/15/2018This project is currently 49% complete and will be fully complete in spring 2019

Recently completed work (since last newsletter) :

- Contractor completed wingwall and support columns for Abut B side of new bridge. Contractor has completed pouring the footer for Abut B side Stage 1 Construction. Contractor has completed the roadway construction on the Abut A side leading up to bridge abutment by placing asphalt

- Current work items/areas:

- Contractor will continue to work on Abut B side of new bridge to prep for placing beam seats and switching traffic

- Upcoming work items/areas over the next month:

- Contractor will continue bridge work on Abut B side

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

- There may be the need for flagging operations throughout this stage of work as needed and the hours they can utilize a flagging operation is 9am-3pm Monday through Friday

 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2020
Construction Fall 2016 Winter 2019
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
10/15/2018This project is currently 49% complete and will be fully complete in spring 2019

Recently completed work (since last newsletter) :

- Contractor completed wingwall and support columns for Abut B side of new bridge. Contractor has completed pouring the footer for Abut B side Stage 1 Construction. Contractor has completed the roadway construction on the Abut A side leading up to bridge abutment by placing asphalt

- Current work items/areas:

- Contractor will continue to work on Abut B side of new bridge to prep for placing beam seats and switching traffic

- Upcoming work items/areas over the next month:

- Contractor will continue bridge work on Abut B side

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work):

- There may be the need for flagging operations throughout this stage of work as needed and the hours they can utilize a flagging operation is 9am-3pm Monday through Friday

 
9/17/2018This project is currently 46% complete and is scheduled to be fully complete in spring 2019.

Recently completed work (since last newsletter)
- Contractor completed Support of Excavation for Abut B side. Contractor has completed pouring the footer for Abut B side Stage 1 Construction. Contractor has completed the roadway construction on the Abut A side leading up to bridge abutment by placing asphalt

- Current work items/areas:

- Contractor currently working forming for pouring the stem wall Abut B side of Stage 1 Construction

- Upcoming work items/areas over the next month:
- Contractor will continue bridge work on Abut B side

Please explain any upcoming work that may be more disruptive than usual (detours, shifts, night work).
- THERE MAY BE THE NEED FOR FLAGGING OPERATIONS THROUGHOUT THIS STAGE OF WORK AS NEEDED AND THE HOURS THEY CAN UTILIZE A FLAGGING OPERATION IS 9AM-3PM MON-FRI
 
6/25/2018This project is currently 41.2% complete and is set to be fully complete spring of 2019.

Recently completed work (since last newsletter)
-Contractor formed and poured the retaining wall for abut a stage 1 construction
-Contractor has begun demo of Abut B
-Contractor completed the waterline relocation work

Current work items/areas:
-Contractor currently working on the roadway construction placing stone to build roadway as part of Stage 1 construction

Upcoming work items/areas over the next month:
-Contractor will continue bridge work on SW quadrant
-Contractor will continue roadway construction and also install underdrain along roadway.
 
5/21/2018This project is currently 39.82% complete and will be complete by this fall.

Recently completed work (since last newsletter)
-Contractor formed and poured the retaining wall for abut a stage 1 construction.

Current work items/areas:
-CONTRACTOR CURRENTLY WORKING ON PLACING stone as backfill for abut a stage 1 construction

Upcoming work items/areas over the next month:
- WORK ON RELOCATION OF WATERLINE AND ALSO CONTINUE BRIDGE WORK ON SW QUADRANT.
 
4/5/2018-CONTRACTOR HAS POURED THE DRAINAGE TROFT AND POURED THE RETAINING WALL FOR THE PROPOSED ABUT A SW QUADRANT
-CONTRACTOR CURRENTLY WORKING ON PLACING 57 STONE AS BACKFILL AND ALSO STRIPPING FORMS FROM DRAINAGE TROFT
-IN THE NEXT MONTH THEY WILL WORK ON RELOCATION OF WATERLINE AND ALSO COTINUE BRIDGE WORK ON SW QUADRANT. CONTINUE WORK ON DRAINAGE SYSTEM
-THERE MAY BE THE NEED FOR FLAGGING OPERATIONS THROUGHOUT THIS STAGE OF WORK AS NEEDED AND THE HOURS THEY CAN UTILIZE A FLAGGING OPERATION IS 9AM-3PM MON-FRI
 
2/1/2018The contractor has poured the footing for the SW abutment. Contractor is placing rebar for wing and stem walls for the SW quadrant.
 
12/21/2017Recently completed work:

- Contractor has installed Support of Excavation, installed 3 micro piles on SW corner of the existing abutment and completed demo of the SW quadrant of existing bridge.
- Contractor has installed Phase 2 stream diversion

Current work items/areas:
- Contractor will begin setting forms and rebar for footing on SW quadrant

 
11/13/2017Recently completed work:
-Crews are finalizing the supports for excavation. The stream diversion is in place.

Current work items/areas:
-Crews will move towards demolition of the bridge and complete the second phase of the stream diversion.
 
9/12/2017-Contractor has installed supports in preparation for bridge demo.
-Crews are placing the stream diversion, at this time.
-Once the stream diversion is in place, the existing bridge will be demolished.
 
7/13/2017Recently completed work (since last newsletter)
-Crews installed a temporary pedestrian bridge and pedestrian path for pedestrians to use while work is in progress on the bridge

Current work items/areas:
-Contractor currently working on excavation in preparation for Demo of the existing bridge

 
5/12/2017Recently completed work (since last newsletter)
- Crews completed traffic switch along with MD 140 EB and WB between Silo Hill
Road and Creamery Road

Current work items/areas:
-Finishing installation of the pedestrian path and excavate for the temporary pedestrian bridge abutments

 
2/16/2017Crews have begun to conduct test pitting and installation of rip rap. Drainage pipe and grading has also been started, in preparation of further construction.
 
1/1/2016Engineering underway.
 
1/1/2001Currently, utility are being relocated so that work can begin on the bridge. Utility relocation will continue throughout the winter.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202