Home
Business Center
Projects & Studies
Commuter & Travel
Safety Programs
Environment & Community
Info Center
State Highway Administration
business center
Projects & Studies
commuter & travel
safety programs
environment & Community
information center
contact us

Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR350_51
US 0040 AL MAIN STREET IVY HILL DRIVE TO MIDDLETOWN PARKWAY
Status
11/16/2017Current Work:
Water main work continues
Curb and gutter placement continues
Paving has been completed from Ivy Hill to Creamery Row

 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2018
Construction Fall 2016 Spring 2019
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
11/16/2017Current Work:
Water main work continues
Curb and gutter placement continues
Paving has been completed from Ivy Hill to Creamery Row

 
9/15/2017Crews continue to place the new water main throughout town.
Sidewalk, curb and gutter work is also being done on the west side of town.
 
7/13/2017Crews are currently working on curb and gutter placement, sidewalk construction, and roadway widening on the west end of the project limits. Crews are also working on storm water management ponds.
 
5/22/2017Crews are installing new waterlines throughout the project limits. Work began at Middletown Parkway and is moving west.
 
1/4/2017Over the winter, crews will continue to complete utility work within the project limits. The contractor will also begin work on the storm water management pond on the west side of the town. As the weather becomes warmer, water main work will begin. Water main work will begin at Middletown Parkway and move west.
 
1/1/2016Engineering and Right-of-Way are underway. Construction to begin during current fiscal year.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202