Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR171_51
MD 0140 MAIN STREET EAST NORTH AVENUE TO TIMBERMILL RUN
Status
9/12/2017Recently completed work
- Have completed this sidewalk, curb and gutter installation on MD 140 EB from Tannery Lane to Ott house prior to the Square of Emmitsburg

Current work items/areas:
- MD 140 EB from Timber Mill Run to Creamery Road

Upcoming work items/areas over the next month:
- Crews will remove and replace existing curb, gutter and sidewalk along MD 140 EB and WB
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way
Construction Spring 2017 Summer 2018
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
9/12/2017Recently completed work
- Have completed this sidewalk, curb and gutter installation on MD 140 EB from Tannery Lane to Ott house prior to the Square of Emmitsburg

Current work items/areas:
- MD 140 EB from Timber Mill Run to Creamery Road

Upcoming work items/areas over the next month:
- Crews will remove and replace existing curb, gutter and sidewalk along MD 140 EB and WB
 
7/12/2017Crew have completed the sidewalk, curb and gutter installation on MD 140 EB from Tannery Lane to Warthens Court.

Crews will now work on MD 140 EB from Tiber Mill Run to Creamery Road. Crews may begin working Concurrently on both east and westbound sides of the road.

MAJOR MD 140 DETOUR FOR TOWN SQUARE WATERLINE WORK WHICH WILL CLOSE THE INTERSECTION OF TOWN SQUARE (MD 140 N.SETON AVE/S.SETON AVE US15 BUS) Weekend operation for tie-ins at intersection and new 4” valve, Square closed to traffic. Detours in place (see map section for detour map). Traffic will be detoured via MD 550 and US 15. Local traffic should use W. Lincoln Ave. and Federal Ave.

•7:00PM FRIDAY JULY 14TH THROUH 5:00AM MONDAY JULY 17TH WHICH WILL CLOSE MD 140 TO COMPLETE THE WATERLINE WORK AT THE TOWN SQUARE

 
1/1/2016Engineering underway.
 
1/1/2001Beginning Friday, July 14th at 7pm until Monday at 5am crews will replace the waterline in the town square. Local traffic will be detoured to W. Lincoln Ave, Federal Ave. and DePaul St. (A detour map can be found under the map tab)
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202