Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR132_21
MD 0355 URBANA PIKE BRIDGE 1008600 OVER BENNETT CREEK
Status
6/28/2018Competitive Electronic Bids were opened on June 28, 2018. The apparent low bidder is Concrete General Inc. of Gaithersburg, MD.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Underway 2018
Right-of-Way Underway 2021
Construction 2019 2020
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
6/28/2018Competitive Electronic Bids were opened on June 28, 2018. The apparent low bidder is Concrete General Inc. of Gaithersburg, MD.
 
5/23/2018Project advertised for competitive bids 05/22/2018.
 
5/14/2018Final design is complete. Right-of-way acquisition and utility relocation has begun. Project is on schedule to advertise on May 22, 2018. Construction is scheduled to begin on September 3, 2018.
 
1/23/2018Project design is approximately 80% complete. The advertisement date will be in Spring 2018 with construction anticipated to begin Fall 2018.

 
10/17/2017Environmental agency coordination continues to obtain necessary environmental permitting.
 
6/21/2017Project design continues. Project limits have recently expanded to include wetland mitigation activities and coordination with environmental agencies is ongoing.
 
3/7/2017Project design is 50% complete. Activities and coordination to identify and mitigate environmental impacts in accordance with the National Environmental Policy Act have been completed.
 
11/17/2016Due to delays in utility design and environmental permitting resulting from recent design adjustments, construction has been moved to spring 2018 through fall 2019.
 
6/8/2016Preliminary Engineering has been completed. Final Engineering on the selected bridge replacement option has begun.
 
2/11/2016Preliminary engineering continues. Traffic studies have been completed and environmental studies are underway.
 
7/28/2015Engineering underway. Construction to begin during budget fiscal year.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202