Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Frederick Project Number:FR102_51
MD 0478 KNOXVILLE ROAD BRIDGE 1008900 OVER BRANCH OF POTOMAC RIVER
Status
6/18/2019This project is approximately 40% complete and expected to finish spring 2020.

The contractor poured the concrete for the wingwall I step footings and began pouring for the wingwall I stem section. The recent early morning concrete pour of 400 cubic yards was required for the Abutment B and wingwall III footing. The excavation for wingwalls II and IV of the new bridge is complete.

The detour on MD 478 remains in effect.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2022
Construction Spring 2018 Spring 2020
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
6/18/2019This project is approximately 40% complete and expected to finish spring 2020.

The contractor poured the concrete for the wingwall I step footings and began pouring for the wingwall I stem section. The recent early morning concrete pour of 400 cubic yards was required for the Abutment B and wingwall III footing. The excavation for wingwalls II and IV of the new bridge is complete.

The detour on MD 478 remains in effect.
 
6/14/2019Please be advised that the MDOT SHA will be working overnight Sunday, June 16 through Monday, June 17 on the new MD 478 bridge in Brunswick.

The overnight work is necessary to complete a large concrete pour of approximately 400 cubic yards for the second footer of the new bridge, similar to the one in April. The concrete trucks will travel on southbound MD 17 to West Potomac Street to access the east side of the MD 478 bridge.

The MDOT SHA apologizes for any inconvenience and thanks everyone for their patience.
 
5/20/2019This project is 31% complete and expected to finish spring 2020.

Recently, concrete was poured for the footing and abutment A of the new bridge. The contractor is currently working on the excavation for abutment B's footing and wingwalls.

The MD 478 detour will remain in place until fall 2019.
 
4/26/2019Please be advised that MDOT SHA will be working overnight this Sunday, April 28 through Monday, April 29 in Brunswick. This work is necessary to complete a large concrete pour of 400 yards for one of the footers of the new MD 478 bridge.

MDOT SHA appreciates your understanding. We are working with the contractor to avoid future overnight work when possible.
 
4/26/2019Please be advised that MDOT SHA will be working overnight this Sunday, April 28 through Monday, April 29 in Brunswick. This work is necessary to complete a large concrete pour of 400 yards for one of the footers of the new MD 478 bridge.

MDOT SHA and the contractor are working to minimize future overnight work when possible, and will keep the community informed.
 
4/15/2019This project is 15% complete and expected to finish spring 2020.

Crews have demolished one side of the bridge and are now excavating that side to construct the new bridge’s footing. Once that side is finished (in approximately two months), work will start on the other side and then the bridge deck.

This section of MD 478 is closed to traffic and a detour is in place to guide motorists. The stream underneath the bridge will be diverted during construction.
 
2/19/2019The contractor is currently awaiting utility relocation.
 
12/10/2018This project is currently awaiting final completion of utility relocation. CGI is scheduled to begin removal of the existing bridge in early February.
 
1/1/2016Engineering and Right-of-way underway. Construction to begin during budget fiscal year.
 
1/1/2001The NTP for this project was 4/12/18. At the pre-construction meeting, the contractor's Super. stated that there's several months worth of utility relocation work that needs done prior to the contractor beginning work on the bridge. According to the Super., they won't be doing any construction work until January, 2019. When work does begin, MD 478 will be closed and a detour will be set up.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202