County:Charles Project Number:CH239_21
MD 0224 RIVERSIDE ROAD BRIDGE 0801900 OVER THORNE GUT AND BRIDGE 0802000 OVER BRANCH THORNE GUT
Status
11/27/2017Final design and permitting activities are complete and the project is on schedule to be advertised for construction bids on December 5, 2017.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Underway 2018
Right-of-Way
Construction 2018 2019
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
11/27/2017Final design and permitting activities are complete and the project is on schedule to be advertised for construction bids on December 5, 2017.
 
8/17/2017Final Engineering and permitting are being completed. Construction to begin during summer, 2018.
 
1/1/2016Engineering underway. Construction to begin during budget fiscal year.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202