Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Calvert Project Number:CA413_53
MD 0002 SOLOMONS ISLAND ROAD IHB - FOX RUN BOULEVARD TO MD 231 (PHASE 2)
Status
11/15/2018The contractor, Total Civil Construction & Engineering have completed work on storm water and sewer lines. Pond excavation is continuing and grading for the roadway widening is ongoing. Main Street to Commerce Lane grading for the road widening and new sidewalk has begun. Curb, gutter and sidewalk have been poured between Fox Run Blvd. and McDonald’s.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2019
Construction Spring 2018 Spring 2020
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
11/15/2018The contractor, Total Civil Construction & Engineering have completed work on storm water and sewer lines. Pond excavation is continuing and grading for the roadway widening is ongoing. Main Street to Commerce Lane grading for the road widening and new sidewalk has begun. Curb, gutter and sidewalk have been poured between Fox Run Blvd. and McDonald’s.
 
9/13/2018The contractor, Total Civil Construction & Engineering continues utility relocation and pipe installation. Verizon has finished with their utility relocation. Washington Gas estimates they will take 4 months to finish their relocation. Stream restoration has begun. Grade work on MD 2/4 to begin in early October.
 
7/12/2018The contractor Total Civil Construction & Engineering (TCCE) continues to work phase 1 of the project. Grubbing has finished, widening of MD 2/4 N/B and MD 402 W/B continues. Phase 2 is targeted to start in November which includes median work and Commerce Lane intersection reconfiguration. A new traffic signal will also be put in at this intersection. Phase 3 should begin in January 2019 and run through July. This work will consist of the widening of MD 2/4 S/B and MD 402 E/B. Stream restoration has begun and will finish by the end of Phase 2 construction.
 
6/12/2018MDOT SHA’s contractor – Total Civil Construction & Engineering – is performing utility work through October 2018. Current work includes:
- Water line and storm drain work along northbound MD 2/4.
- Storm drain work on MD 402: Concrete barrier wall will soon be added so crews may perform daytime and nighttime work.
 
1/1/2016Engineering underway. Right-of-Way to begin during current fiscal year. Construction to begin during budget fiscal year.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202