Home
Business Center
Projects & Studies
Commuter & Travel
Safety Programs
Environment & Community
Info Center
State Highway Administration
business center
Projects & Studies
commuter & travel
safety programs
environment & Community
information center
contact us

Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Baltimore Project Number:BA729_21
MD 0140 REISTERSTOWN ROAD NORTH OF PAINTERS MILL ROAD TO NORTH OF OWINGS MILLS OVERPASS (PHASE 2)
Status
10/8/2008Engineering 65% complete
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Pending
Right-of-Way
Construction
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
10/8/2008Engineering 65% complete
 


Events

No events found at this time.
 