Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Baltimore Project Number:BA729_21
MD 0140 REISTERSTOWN ROAD NORTH OF PAINTERS MILL ROAD TO NORTH OF OWINGS MILLS OVERPASS (PHASE 2)
Status
9/6/2017Continues preparing an alternate stormwater management (SWM) concept that would minimize properties impacts along the corridor. An advertisement date for the project has been deferred until an alternate SWM concept is approved.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Underway 2018
Right-of-Way
Construction
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
9/6/2017Continues preparing an alternate stormwater management (SWM) concept that would minimize properties impacts along the corridor. An advertisement date for the project has been deferred until an alternate SWM concept is approved.
 
6/5/2017Currently preparing an alternate stormwater management (SWM) concept in order to minimize properties impacts along the corridor.

An advertisement date for the project has been deferred until an alternate SWM concept is approved.
 
11/17/2016Surveyors may be observed throughout the project limits during the month of November, December and January. They are test pitting to determine the specific elevations of existing utilities, conducting engineering studies including soil borings for stormwater management facilities, and collecting additional topographic information to continue the drainage design for the project.
 
1/28/2015Funding for the MD 140 (Reisterstown Road) Phase 2 from North of Painters Mill Road to North of Owings Mills Boulevard Overpass project has been restored and Final Engineering is currently underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202