Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Baltimore Project Number:BA727_51
IS 0695 BALTIMORE BELTWAY SRI - OUTER LOOP - SOUTH OF US 40 TO MD 144
Status
1/4/2018CONSTRUCTION UPDATE - WINTER 2018

Contractor crews will continue construction work as weather permits during winter 2018 along southbound I-695 (Beltway Outer Loop) between south of Exit 15, the US 40 (National Pike) interchange and Exit 13, the MD 144 (Frederick Road) interchange.

All four travel lanes on southbound I-695 (Beltway Outer Loop) will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday. Most highway construction work will be done behind concrete barriers placed along the outside shoulders of the Outer Loop; however, there may be temporary single and multiple lane closures on the Outer Loop during off-peak hours, mostly at night.

Digital message signs will advise travelers in advance of any temporary overnight lane closures and ramp detours this winter.

In spring 2018, MDOT SHA will begin long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2018
Construction Fall 2015 Fall 2019
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic: Fall 2019
 
Status Updates
 
1/4/2018CONSTRUCTION UPDATE - WINTER 2018

Contractor crews will continue construction work as weather permits during winter 2018 along southbound I-695 (Beltway Outer Loop) between south of Exit 15, the US 40 (National Pike) interchange and Exit 13, the MD 144 (Frederick Road) interchange.

All four travel lanes on southbound I-695 (Beltway Outer Loop) will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday. Most highway construction work will be done behind concrete barriers placed along the outside shoulders of the Outer Loop; however, there may be temporary single and multiple lane closures on the Outer Loop during off-peak hours, mostly at night.

Digital message signs will advise travelers in advance of any temporary overnight lane closures and ramp detours this winter.

In spring 2018, MDOT SHA will begin long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway.
 
10/16/2017CONSTRUCTION UPDATE - FALL 2017

During fall 2017 and winter 2018, contractor crews will continue construction work as weather permits along southbound I-695 (Beltway Outer Loop) between south of Exit 15, the US 40 (National Pike) interchange and Exit 13, the MD 144 (Frederick Road) interchange.

All four travel lanes on southbound I-695 (Beltway Outer Loop) will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday.

Most highway construction work will be done behind concrete barriers placed along the outside shoulders of the Outer Loop; however, there may be temporary single and multiple lane closures on the Outer Loop during off-peak hours, mostly at night. Digital message signs will advise travelers in advance of any temporary lane closures and ramp detours.

In spring 2018, MDOT SHA will begin long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway.

This web page will provide periodic updates on the construction project; for daily traffic conditions and lane/ramp closures, use the free Maryland 511 system. Call 511 on your hands-free cell device or log onto www.md511.org to get personalized alerts for your commute. Please drive with caution and observe the 55 mph speed limit on I-695.

SafeZones Automated Speed Enforcement (cameras) are in effect along southbound I-695 south of the US 40 interchange for this work zone. For more information and other work zone enforcement locations, visit the SafeZones website, www.safezones.maryland.gov
 
4/25/2017CONSTRUCTION UPDATE - WINTER 2017

During spring 2017, contractor crews will continue construction work as weather permits along southbound I-695 (Beltway Outer Loop) between south of the US 40 (National Pike) interchange and the MD 144 (Frederick Road) interchange.

All four travel lanes on southbound I-695 (Beltway Outer Loop) will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday.

Most highway construction work will be done behind concrete barriers placed along the outside shoulders of the Outer Loop; however, there may be temporary single and multiple lane closures on the Outer Loop during off-peak hours. Digital message signs will advise travelers in advance of any temporary lane closures and ramp detours.

In summer 2017, MDOT SHA will begin long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway. This web page will provide periodic updates on the construction project; for daily traffic conditions and lane/ramp closures, use the free Maryland 511 system. Call 511 on your hands-free cell device or log onto www.md511.org to get personalized alerts for your commute.

Please drive with caution and observe the 55 mph speed limit on I-695. SafeZones Automated Speed Enforcement (cameras) are in effect on southbound I-695 south of the US 40 interchange for this work zone. In accordance with Maryland law, images are only captured and used for the purpose of issuing a citation if a vehicle is exceeding the posted work zone speed limit by 12 mph or greater. The fine is $40.00. For more information and other work zone enforcement locations, visit the SafeZones website, www.safezones.maryland.gov 1
 
1/24/2017CONSTRUCTION TRAFFIC ALERT: EDMONDSON AVE. TO BE CLOSED UNDERNEATH I-695 ON WEEKEND OF JANUARY 27 - 30; DETOURS IN EFFECT

Weather permitting, the Maryland Department of Transportation’s State Highway Administration plans to temporarily close and detour the section of Edmondson Avenue underneath I-695 (Baltimore Beltway Inner and Outer Loop) the weekend of January 27.

Digital message signs are in place to alert motorists to the upcoming weekend road closure and detour, which will begin 7 p.m. Friday, January 27 and end by 5 a.m. Monday, January 30. The detour will allow contractor crews to more safely perform demolition work on the Outer Loop side of the I-695 bridge over Edmondson Avenue.

Traffic on eastbound Edmondson Avenue will be diverted onto the I-695 Outer Loop, through the MD 144 (Frederick Road) interchange, onto the I-695 Inner Loop, and back to Edmondson Avenue east of I-695.

Traffic on westbound Edmondson Avenue will be diverted onto the I-695 Inner Loop to the US 40 (National Pike) interchange, onto eastbound US 40, onto southbound Ingleside Avenue and back southbound Ingleside Avenue, traveling under I-695 and back to Edmondson Avenue west of I-695.

This work is part of SHA’s $68 million project to reconstruct and widen the I-695 Outer Loop between south of US 40 and MD 144. In case of inclement weather, the weekend road closure and detour will take place on the next possible weekend.

Local residents with questions or concerns may call SHA’s construction project field office in Catonsville at 410-975-4812.
 
1/3/2017CONSTRUCTION UPDATE - WINTER 2017

During winter 2017, contractor crews will continue construction work as weather permits along southbound I-695 (Beltway Outer Loop) between south of the US 40 (National Pike) interchange and the MD 144 (Frederick Road) interchange.

All four travel lanes on southbound I-695 (Beltway Outer Loop) will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday.

During this phase of construction, most construction work will be done behind concrete barriers placed along the outside shoulders of the Outer Loop; however, there may be temporary single and multiple lane closures on the Outer Loop during off-peak hours.

Digital message signs will advise travelers in advance of any temporary lane closures and ramp detours.

In future phases of the project, beginning mid-2017, there will be long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway.

This web page will provide periodic updates on the construction project; for daily traffic conditions and lane/ramp closures, use the free Maryland 511 system. Call 511 on your hands-free cell device or log onto www.md511.org to get alerts for incidents and road work locations. The website allows you to create a personal commuter account to receive updates from the Maryland 511 system.

Please drive with caution and observe the 55 mph speed limit on I-695. SafeZones Automated Speed Enforcement (cameras) are in effect on southbound I-695 south of the US 40 interchange for this work zone. In accordance with Maryland law, images are only captured and used for the purpose of issuing a citation if a vehicle is exceeding the posted work zone speed limit by 12 mph or greater. The fine is $40.00. For more information and other work zone enforcement locations, visit the SafeZones website, www.safezones.maryland.gov
 
10/27/2016CONSTRUCTION UPDATE - FALL 2016

During fall 2016, contractor crews will continue construction work along southbound I-695 (Beltway Outer Loop) to prepare for widening the highway between south of US 40 (National Pike) and MD 144 (Frederick Road).

All four travel lanes on southbound I-695 in the work zone will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday.

During this phase of construction, most work will be done behind concrete barriers placed along the outside shoulders of I-695; however, there may be temporary single and multiple lane closures on I-695 during off-peak hours. Digital message signs will advise travelers in advance of any temporary lane closures and ramp detours.

In future phases of the project, beginning mid-2017, there will be long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway.

This web page will provide periodic updates on the construction project; for daily traffic conditions and lane/ramp closures, "know before you go" and use the free Maryland 511 system.

Call 511 on your hands-free cell device or visit the Maryland 511 website, www.md511.org to get alerts for incidents and road work locations. The website allows you to create a personal commuter account to receive updates from the Maryland 511 system.

Please drive with caution and observe the 55 mph speed limit on I-695. SafeZones Automated Speed Enforcement (cameras) are in effect on southbound I-695 south of the US 40 interchange for this work zone. In accordance with Maryland law, images are only captured and used for the purpose of issuing a citation if a vehicle is exceeding the posted work zone speed limit by 12 mph or greater. The fine is $40.00.

For more information and other work zone enforcement locations, visit the SafeZones website, www.safezones.maryland.gov
 
7/14/2016CONSTRUCTION UPDATE - SUMMER 2016

During summer 2016, contractor crews will continue construction work to prepare for widening the highway. All four travel lanes on southbound I-695 (Beltway Outer Loop) will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday.

During this phase of construction, most work will be done behind concrete barriers placed along the outside shoulders of the Outer Loop; however, there may be temporary single and multiple lane closures on the Outer Loop during off-peak hours. Digital message signs will advise travelers in advance of any temporary lane closures and ramp detours.

In future phases of the project, beginning mid-2017, there will be long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway.

This web page will provide periodic updates on the construction project; for daily traffic conditions and lane/ramp closures, use the free Maryland 511 system.

Call 511 on your hands-free cell device or log onto www.md511.org to get alerts for incidents and road work locations. The website allows you to create a personal commuter account to receive updates from the Maryland 511 system.
 
4/1/2016CONSTRUCTION UPDATE - SPRING 2016

During spring 2016, contractor crews will continue construction work to prepare for widening the highway, such as: earthwork, excavation and leveling of the ground along the I-695 outer loop; building a new retaining wall at Edmondson Avenue; preparing for construction of a noise wall at Frederick Road; and installation of chain link fence along the I-695 outer loop in the vicinity of Ingleside Avenue.

All four travel lanes on the Outer Loop will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday.

Most of the construction work will be done behind concrete barriers; however, there may be temporary single and multiple lane closures on outer loop of I-695 during off-peak hours.

In the future, there will be long-term interchange ramp closures/detours when necessary to realign the existing ramps to the new width and height of the widened roadway.

Digital message signs will advise travelers in advance of traffic pattern changes, lane closures and ramp detours.

This web page will provide periodic updates on the construction project; for daily traffic conditions and lane/ramp closures, use the free Maryland 511 system.

Call 511 on your hands-free cell device or log onto www.md511.org to view highway system maps and alerts for incidents and road work locations, and create a personal commuter account to receive updates from 511.
 
2/9/2016CONSTRUCTION UPDATE - WINTER 2016

During winter 2016, contractor crews will work as weather permits to prepare for widening the highway, such as utility relocations; removing metal barriers, land clearing and grubbing, and excavation work.

All four travel lanes on the Outer Loop will remain open during peak travel hours: 5 a.m. - 9 a.m. and 3 p.m. - 7 p.m. Monday through Friday.

Most of the construction work will be done behind concrete barriers; however, there may be temporary lane closures during off-peak hours.

In the future, there will be long-term interchange ramp closures/detours when necessary to realign the ramps to the new width and height of the widened roadway.

Digital message signs will advise travelers in advance of traffic pattern changes, lane closures and ramp detours.

This web page will provide periodic updates on the project; for daily traffic conditions and lane/ramp closures, use the free Maryland 511 system.
 
11/4/2015CONSTRUCTION UPDATE - FALL 2015

Contractor crews have begun preliminary site work, such as placement of construction signs, barriers and equipment along the Outer Loop within the project limits, between south of the US 40 interchange and the MD 144 interchange.

Beginning early November 2015, crews will shift traffic lanes along the Outer Loop within the project limits, reduce the width of the lanes along the Outer Loop to 11 feet wide and install concrete traffic barriers alongside the shoulders to create a safer construction work zone.

During late fall 2015 and winter 2016, contractor crews will perform various activities to prepare for widening the highway, such as utility relocations; removing metal barriers, land clearing and grubbing, and excavation work.

All four travel lanes on the Outer Loop will remain open during peak travel hours; however, there will be temporary lane closures during off-peak hours.

In the future, there will be long-term interchange ramp closures/detours when necessary to realign the ramps to the new width and height of the widened roadway. Digital message signs will advise travelers in advance of traffic pattern changes, lane closures and ramp detours.

This web page will provide periodic updates on the progress of the project; for daily traffic conditions and lane/ramp closure, use the free Maryland 511 system for 24-hour updates.

 
9/14/2015SHA issued a "Notice to Proceed" to the contractor, to begin the construction phase of the project.
 
8/26/2015SHA awarded the construction contract to Tutor Perini Corporation of Rochelle, NY & Cherry Hill Construction of Jessup, MD.
 
10/22/2014Community Informational Meeting held at Catonsville Elementary School.
 
1/1/2013Engineering underway for the segment from MD 144 to south of US 40.
 


Events

   Community Informational Meeting

Date:

2/24/2015   (View Document)
Location:100 Kenwood Avenue, Baltimore ,MD 21228
 
   Community Informational Meeting

Date:

10/22/2014   (View Document)
Location:615 Frederick Road, Catonsville ,MD 21228
 
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202