Project Schedule & Events

Project Schedule Documents Contacts Map(s) Media Feedback FAQ
 
County:Baltimore Project Number:BA465_51
MD 0147 HARFORD ROAD AT GLEN ARM/ MT VISTA ROAD
Status
4/5/2018FINAL PAVING WORK - SPRING 2018

On December 21, 2017 SHA and Kinsley Construction re-opened the Mt. Vista Road leg of the roundabout to create the final traffic pattern for the new roundabout.

In spring 2018, contractor crews will return to the new roundabout to complete final paving work on Harford Road, Mt. Vista Road and Glen Arm Road within the project limits. Digital message boards will be posted in advance of pavement work.

Lane Closures and Flagging Operations in Roundabout:

• Temporary daytime lane closures on Harford Road in the vicinity of the Glen Arm Road/Mt. Vista Road roundabout (9 a.m. – 3 p.m., Monday through Friday)

• Temporary flagging operations controlling two-way traffic on Harford Road (9 a.m. – 3 p.m., Monday through Friday)
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2020
Construction Summer 2016 Spring 2018
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic: Spring 2018
 
Status Updates
 
4/5/2018FINAL PAVING WORK - SPRING 2018

On December 21, 2017 SHA and Kinsley Construction re-opened the Mt. Vista Road leg of the roundabout to create the final traffic pattern for the new roundabout.

In spring 2018, contractor crews will return to the new roundabout to complete final paving work on Harford Road, Mt. Vista Road and Glen Arm Road within the project limits. Digital message boards will be posted in advance of pavement work.

Lane Closures and Flagging Operations in Roundabout:

• Temporary daytime lane closures on Harford Road in the vicinity of the Glen Arm Road/Mt. Vista Road roundabout (9 a.m. – 3 p.m., Monday through Friday)

• Temporary flagging operations controlling two-way traffic on Harford Road (9 a.m. – 3 p.m., Monday through Friday)
 
12/19/2017CONSTRUCTION TRAFFIC ALERT - DECEMBER 2017

Mt. Vista Road to Re-open to Traffic on or about December 21

Weather permitting, MDOT SHA's contractor Kinsley Construction is planning to have the Mt. Vista Road leg of the new roundabout re-opened to traffic on December 21, 2017 at approximately 3 p.m. The re-opening of Mt. Vista Road is the final traffic pattern for the new roundabout.

In spring 2018, contractor crews will return to the new roundabout to complete final paving work on Harford Road, Mt. Vista Road and Glen Arm Road within the project limits.

 
11/1/2017FALL 2017 CONSTRUCTION TRAFFIC ALERT- NEW TRAFFIC PATTERN AND ROUNDABOUT TO START NOVEMBER 8

Weather permitting, on Wednesday, November 8, 2017 the Maryland Department of Transportation State Highway Administration (MDOT SHA) will set a new traffic pattern at the intersection of Harford Road with Glen Arm Road and Mt. Vista Road.

Crews will create a temporary roundabout, re-open the Glen Arm Road leg of the roundabout and temporarily close the Mt. Vista Road leg. Mt. Vista Road will be closed at Harford Road for approximately six weeks.

Northbound and southbound Harford Road will remain open to traffic during the third phase of work, which includes construction of the center roundabout island and medians, tree planting and landscaping.

This is the third phase of the $3.7 million project to construct a new roundabout at the Harford Road (MD 147) intersection with Glen Arm and Mt. Vista roads in Baltimore County.

Residents, commuters and commercial vehicle drivers should plan for extra travel time along Harford Road and along the Mt. Vista Road detour route in November and December 2017. Reflective barrels and signs will guide travelers through the temporary roundabout.

MDOT SHA will post signs for the following detour route for Mt. Vista Road: Harford Road to Sunshine Avenue to Belair Road to Mt. Vista Road.

Mt. Vista Road will re-open in late December 2017, weather permitting.

Final paving work on the new roundabout will be performed spring 2018.
 
6/20/2017SUMMER 2017 TRAFFIC ALERT: TRAFFIC PATTERN AT HARFORD ROAD ROUNDABOUT CHANGES JUNE 22

MDOT SHA to Close and Detour the Glen Arm Leg of the Harford Road/Glen Arm Road/Mt. Vista Road Intersection for Three Months; Reopening Mt. Vista Road at Harford Road

Weather permitting, beginning 9 a.m. Thursday, June 22, the Maryland Department of Transportation State Highway Administration (MDOT SHA) will temporarily close access to Glen Arm Road at MD 147 (Harford Road) as crews begin the final phase of the $3.7 roundabout installation at the Harford Road (MD 147) intersection with Glen Arm and Mt. Vista roads in Baltimore County.

Simultaneously, crews will re-open access to Mt. Vista Road at MD 147, which has been closed since last summer to construct the first half of the roundabout. Glen Arm Road will be closed at Harford Road until early fall, weather permitting.
Northbound and southbound Harford Road will remain open to traffic during construction.

MDOT SHA will post signs with the following detour route during the temporary Glen Arm Road closure: Harford Road to Long Green Pike to Glen Arm Road.
(Detour map is available on this project webpage under Maps)

Commuters and commercial vehicle drivers should plan for extra travel time on Harford Road and the detour routes during the next year. The new roundabout should be complete by late fall, weather permitting.
 
12/22/2016CONSTRUCTION UPDATE - WINTER 2017

As of October 2016, SHA has closed the Mt. Vista Road leg of the intersection for the first of three phases of the roundabout construction.

Harford Road will be open during construction, however, motorists traveling on Harford Road within the Glen Arm, Kingsville, Long Green, and Fork communities should expect the following driving conditions during the roundabout construction:

• A closure and detour of either the Mt. Vista Road or Glen Arm Road legs of the four-way intersection:

Phase 1: (underway 2016-2017) Mt. Vista Road closed at Harford Road (5 – 7 months) Detour Route: Sunshine Avenue and Belair Road

Phase 2: (future 2017) Glen Arm Road closed at Harford Road (2 - 3 months) Detour Route: Long Green Pike and Fork Road

Phase 3: (future 2017) Mt. Vista Road closed at Harford Road (3 - 4 weeks) Detour Route: Sunshine Avenue and Belair Road

• Temporary daytime lane closures on Harford Road in the vicinity of the Glen Arm Road/Mt. Vista Road intersection (9 a.m. – 3 p.m., Monday through Friday)

• Temporary flagging operations controlling two-way traffic on Harford Road (9 a.m. – 3 p.m., Monday through Friday)

Crews will work as weather permits during winter 2017. Please plan ahead for extra travel time in the work zone are and drive with caution in the work zone and detour route.
 
9/26/2016CONSTRUCTION UPDATE - FALL 2016

***Traffic Alert***

On October 5, weather permitting, SHA will close the Mt. Vista Road leg of the intersection to begin the first of three phases of the roundabout construction.

During construction, SHA’s contractor, Kinsley Construction, Inc. of Timonium, will use portable digital message signs in the vicinity of the intersection to alert motorists of long-term closures of Mt. Vista Road or Glen Arm Road at Harford Road.

Although Harford Road will be open during construction, motorists traveling on Harford Road within the Glen Arm, Kingsville, Long Green, and Fork communities should expect the following driving conditions during the roundabout construction:

• A closure and detour of either the Mt. Vista Road or Glen Arm Road legs of the four-way intersection, beginning October 5, 2016:


Phase 1:
Mt. Vista Road closed at Harford Road (5 – 7 months)
Detour Route: Sunshine Avenue and Belair Road


Phase 2:
Glen Arm Road closed at Harford Road (2 - 3 months)
Detour Route: Long Green Pike and Fork Road


Phase 3:
Mt. Vista Road closed at Harford Road (3 - 4 weeks)
Detour Route: Sunshine Avenue and Belair Road


• Temporary daytime lane closures on Harford Road in the vicinity of the Glen Arm Road/Mt. Vista Road intersection
(9 a.m. – 3 p.m., Monday through Friday)

• Temporary flagging operations controlling two-way traffic on Harford Road
(9 a.m. – 3 p.m., Monday through Friday)
 
1/1/2016Construction underway.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202