County:Baltimore Project Number:BA080_51
MD 0137 MOUNT CARMEL ROAD IHB - BRIDGE 03050 OVER I-83
Status
1/8/2018CONSTRUCTION UPDATE - WINTER 2018

MDOT SHA and its contractor opened the temporary bridge carrying MD 137 traffic over I-83 fall 2017 and demolished the old bridge by late fall 2017.

Crews will work on construction of the new bridge as weather permits winter 2018. The temporary bridge will be in effect until the new bridge construction is complete and open to traffic in fall 2018.

Please look ahead for changed traffic patterns in the vicinity of the interchange area and drive with caution in the work zone.

The MDOT SHA Park and Ride Lot at the I-83/Mt. Carmel Road interchange will remain open during construction. Please enter and exit the lot with caution and look ahead for commuters, construction personnel and equipment moving within the lot.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning
Engineering Complete
Right-of-Way Underway 2021
Construction Spring 2017 Winter 2018
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic: Fall 2018
 
Status Updates
 
1/8/2018CONSTRUCTION UPDATE - WINTER 2018

MDOT SHA and its contractor opened the temporary bridge carrying MD 137 traffic over I-83 fall 2017 and demolished the old bridge by late fall 2017.

Crews will work on construction of the new bridge as weather permits winter 2018. The temporary bridge will be in effect until the new bridge construction is complete and open to traffic in fall 2018.

Please look ahead for changed traffic patterns in the vicinity of the interchange area and drive with caution in the work zone.

The MDOT SHA Park and Ride Lot at the I-83/Mt. Carmel Road interchange will remain open during construction. Please enter and exit the lot with caution and look ahead for commuters, construction personnel and equipment moving within the lot.
 
1/10/2017MDOT SHA advertised the MD 137 bridge over I-83 bridge replacement project for bids on January 10, 2017
 
1/1/2013Engineering underway. Construction to begin during budget fiscal year.
 


Events

No events found at this time.
 
RSS
 
 
   
 

RESOURCES


Maryland 511 System

Maryland 511 System:
Free Traffic
and
Travel
Information
Maryland Safe Zones
Maryland Safe Zones:
Automated Speed
Enforcement
in Highway
Work Zones
 
707 North Calvert Street Baltimore, Maryland 21202