County:Anne Arundel Project Number:AT198_11
MD 0003 ROBERT CRAIN HIGHWAY MD 32 TO US 50
Status
8/14/2013The Final Environmental Impact Statement (FEIS) was signed by the Federal Highway Administration on March 3, 2011. We are working on the Design Approval Package and seeking a signature on the Record of Decision (ROD). Currently, SHA and FHWA are working together to ensure that the project complies with the FHWA memorandum "Transportation Planning Requirements and Their Relationship to NEPA Process Completion" reissued on February 9, 2011.
 
Phase Time Frame As Defined in the Consolidated Transportation Program (Funded Year Displayed in CTP)
What's Involved? Estimate Begin Estimate Complete
Planning Underway 2013
Engineering
Right-of-Way Pending
Construction
Completed Milestones
Planning Phase Begin Project Planning
  Alternates Public Workshop
  Location/Design Public Hearing
  Location/Design Approval
Engineering Phase Begin Preliminary Engineering
  Geometric Design Approval
  Final Engineering Complete
  Advertised for Bid    
Construction Phase For General Lane Closure Information click HERE
  Begin Construction (Notice To Proceed)
  Open to Traffic:
 
Status Updates
 
8/14/2013The Final Environmental Impact Statement (FEIS) was signed by the Federal Highway Administration on March 3, 2011. We are working on the Design Approval Package and seeking a signature on the Record of Decision (ROD). Currently, SHA and FHWA are working together to ensure that the project complies with the FHWA memorandum "Transportation Planning Requirements and Their Relationship to NEPA Process Completion" reissued on February 9, 2011.
 
7/27/2011The Final Environmental Impact Statement (FEIS) was signed by the Federal Highway Adminstration on March 3, 2011. We are currently working on the Design Approval Package and seeking a signature on the Record of Decision (ROD).
 
4/4/2011The Final Environmental Impact Statement (FEIS) was signed by the Federal Highway Adminstration on March 3, 2011. We are currently working on the Design Approval Package and seeking a signature on the Record of Decision (ROD).
 
9/1/2010The MD 3 Project Planning Study is currently on hold until further notice. We are currently waiting for the Prince George's County's portion of the project to be added back into the Constrained Long Range Plan (CLRP).
 
6/30/2010The MD 3 Project Planning Study is currently on hold until Fall 2010. We are currently waiting for the Prince George's County's portion of the project to be added back into the Constrained Long Range Plan (CLRP). The Record of Decision is expected to be approved by Federal Highway Administration this Fall/Winter 2010.
 
3/23/2010The MD 3 Project Planning Study is currently addressing comments on the Final Environmental Impact Statement from the Federal Highway Administration (FHWA). The Record of Decision is expected to be approved by FHWA this Summer 2010.
 
1/4/2010The MD 3 Project Planning Study is currently on hold until February 2010. The Record of Decision is expected to be approved by Federal Highway Administration this Summer 2010.
 
10/6/2009The environmental regulatory agencies have agreed to remove the conceptual mitigation from this project; therefore, they will only be concurring on the SHA Selected Alternate. Concurrence is due the end of this month.
 
8/4/2009The Selected Alternate/Conceptual Mitigation (SACM) package is awaiting concurrence from the environmental regulatory agencies.
 
3/3/2009The Selected Alternate/Conceptual Mitigation (SACM)package has been finalized and sent to the Federal regulatory agencies for their final review and concurrence. Once we receive concurrence, the study team will begin to prepare the Final Environmental Impact Statement (FEIS).
 
11/12/2008The team is still addressing comments received from the environmental agencies regarding wetland and waters of the US impacts and mitigation sites.
 
8/19/2008Ongoing coordination with the environmental agencies regarding wetland and waters of the US impacts mitigation sites.
 
6/6/2008Ongoing coordination with the environmental agencies regarding wetland and waters of the US impacts mitigation sites.
 
3/4/2008The Selected Alternate/Conceptual Mitigation (SACM)package has been finalized and resent to the federal regulatory agencies for their final review and concurrence.
 
1/2/2008Comments received from the participating state and federal regulatory agencies have been addressed and the SHA Selected Alternate/Conceptual Mitigation concurrence package is being finalized. Details on the SHA Selected Alternate (Alternate 3 – Boulevard Concept) are provided on this website under Project Information.

 
10/31/2007Ongoing coordination with the environmental agencies.
 
4/23/2007Public Notice for PM 2.5 Conformity Determmination added for review and comment.
 
4/11/2007Ongoing coordination with communities and regulatory agencies. Met with the Greater Crofton Council on March 20, 2007 and the Severn River Commission on April 5, 2007.
 
5/20/2004Held Location/Design Public Hearing.
 
3/31/2004Draft Environmental Impact Statement (DEIS) signed.
 
5/30/2003Received Concurrence: Alternates Retained for Detailed Study (ARDS)
 
11/7/2002Alternates Public Workshop
 
1/31/2002Received Purpose & Need Concurrence
 
10/31/2001Scoping Meeting
 
7/2/2001Project Initiation
 


Events

No events found at this time.
 